Time and Work Questions

Multiple choice
  1. If statement I alone is sufficient but statement II alone is not sufficient

  2. If statement II alone is sufficient but statement I alone is not sufficient

  3. If each statement alone (either I or II) is sufficient

  4. If statement I and II together are sufficient, but neither statement alone is sufficient

  5. If statement I and II together are not sufficient

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Statement I: A completes 1/3 work at 80% efficiency in 20 days. At 100% efficiency, A would complete (1/3) × (100/80) = 5/12 work in 20 days. So A's rate = (5/12)/20 = 5/240 = 1/48 work per day. Statement II: B is 20% more efficient than A, so B's rate = 1.2 × (1/48) = 1.2/48 = 1/40 work per day. However, we don't know who starts first or the order of work. The question asks about A and B working on alternate days, but doesn't specify the starting day. Without this information, we cannot determine the exact time. Even with both statements, key information is missing.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity I < Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or relation can’t be established

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Quantity I: B takes 20 days, so B's rate = 1/20. C is twice as efficient, so C's rate = 2/20 = 1/10 (C takes 10 days). A takes 2 days more than C, so A takes 12 days (rate = 1/12). Combined rate of A, B, C = 1/12 + 1/20 + 1/10 = 5/60 + 3/60 + 6/60 = 14/60 = 7/30. For 7 works: Time = 7 ÷ (7/30) = 30 days. Quantity II: A works for 6 days at rate 1/24, completing 6/24 = 1/4 of work. Remaining work = 3/4. With A, B, C working together at rate 1/24 + 1/30 + 1/40 = 5/120 + 4/120 + 3/120 = 12/120 = 1/10, time needed = (3/4) ÷ (1/10) = 7.5 days. Total time = 6 + 7.5 = 13.5 days. Since 30 > 13.5, Quantity I > Quantity II.

Multiple choice
  1. Statement A alone is sufficient to answer the question but statement B alone is not sufficient to answer the questions.

  2. Statement B alone is sufficient to answer the question but statement A alone is not sufficient to answer the question.

  3. Both the statements taken together are necessary to answer the questions, but neither of the statements alone is sufficient to answer the question.

  4. Either statement A or statement B by itself is sufficient to answer the question.

  5. Statements A and B taken together are not sufficient to answer the question.

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Statement A: Ratio m:w = 3:2. From 4m+18w = 2.5 days work, can find individual rates. Then 12w time = work/12w. Statement B: 6m+6w = 4 days, gives combined rate. With A's ratio or B's data alone, each is sufficient. Answer D is correct.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≤ Quantity II

  3. Quantity I = Quantity II or No relation

  4. Quantity I < Quantity II

  5. Quantity I ≥ Quantity II

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work rates: 12 men in 10 days, so 1 man's rate = 1/(120) work/day. 18 women in 20 days, so 1 woman's rate = 1/(360) work/day. 27 children in 20 days, so 1 child's rate = 1/(540) work/day. 9 women + 9 children work for 16 days: work done = 16 × (9/360 + 9/540) = 16 × (1/40 + 1/60) = 16 × (5/120) = 2/3. Remaining work = 1/3. Men needed = (1/3) / (1/120) = 40. Quantity I = 40, Quantity II = 36. Since 40 > 36, option A is correct.

Multiple choice
  1. Either statement I or II or III alone is sufficient.

  2. Either statement III alone is sufficient or statement I and II together are sufficient.

  3. Either statement II alone is sufficient or statement I and III together are sufficient.

  4. Either statement I and II or statement II and III together are sufficient.

  5. Any of the two statements together are sufficient.

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Statement III alone is sufficient because it directly gives D:C efficiency ratio as 1:2. Since A+B+C complete work in 4 days, and we have the relationship between (A+B) doing 25% work and (D+C) doing 150% more than 1/10th (i.e., 25% of work), we can equate: (A+B) time = (D+C) time. This with the D:C ratio gives individual efficiencies, hence D's time alone. Statements I and II together also work: I gives A:D = 5:3, II gives B:C = 2:3, combined with the work relationship allows solving.

Multiple choice
  1. Only II केवल II

  2. Only I केवल I

  3. Both from I and II I और II दोनों से

  4. Any one of the two. दोनों में से कोई एक

  5. None of these. इनमें से कोई नहीं।

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A+B together take x days. Statement I: A takes x+4 days. Statement II: B takes A+5 days = x+9 days. Together: 1/x = 1/(x+4) + 1/(x+9). Solving gives x=6. Both statements needed. Option C is correct.

Multiple choice

The following questions are accompanied by three statements. You have to determine which statement (s) is/are/suffcient/ necessary to answer the question ? नीचे दिये गये प्रश्नों में तीन कथनों के माध्यम से कुछ जानकारियां दी गई है आपको यह निर्णय करना है कि क्या कथनों में दी गयी जानकारी उत्तर देने के लिए पर्याप्त है। X,Y and Z together will finish the work in how many days? (A) X does half as much work as Y and Y does half as much work as X and Z do together in one day. (B) Y does the whole work in 40 days (C) X and Z do the whole work in 20 days X, Y और Z मिलाकर एक काम को कितने दिनों में पूरा करेंगे ? (A) Y जितना कार्य एक दिन में करता है उसका आधा भाग X करता है। X और Z दोनों मिलकर जितना कार्य करते हैं Y उसका आधा भाग कार्य करता है। (B) Y अकेले पूरे कार्य को 40 दिनों में करता है। (C) X और Z दोनों मिलकर कार्य को 20 दिनों में पूरा करते हैं।

  1. All A,B & C are required A, B और C सभी कथन पर्याप्त है।

  2. A,B &C even together is not sufficient A, B और C सभी कथन पर्याप्त नहीं है।

  3. Either A or B or C sufficient या तो A या B या C पर्याप्त हैं।

  4. Either A and B together or B and C together or C and A together are sufficient. या तो A और B साथ-साथ या B और C साथ-साथ या A और C साथ-साथ पर्याप्त है।

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

From statement B: Y completes work in 40 days, so Y's 1 day work = 1/40. From statement C: X and Z together complete work in 20 days, so (X+Z)'s 1 day work = 1/20. This means X and Z together are twice as efficient as Y. All three together: (X+Y+Z)'s 1 day work = 1/20 + 1/40 = 3/40. Time taken = 40/3 days. Statements B and C together are sufficient.

Multiple choice
  1. Quantity II > Quantity I मात्रा II > मात्रा I

  2. Quantity I ≥ Quantity II मात्रा I ≥ मात्रा II

  3. Quantity I > Quantity II मात्रा I > मात्रा II

  4. Quantity I ≤ Quantity II मात्रा I ≤ मात्रा II

  5. Quantity I = Quantity II or the relation cannot be established संबंध स्थापित नहीं किया जा सकता या मात्रा I = मात्रा II

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

For Quantity I: Let Q take x days, P takes (x+5) days. Working together: 1/x + 1/(x+5) = 1/6. Solving gives x = 10, so sum = 10 + 15 = 25 days. For Quantity II: A's efficiency is 8/13 of B, so A takes 13/8 times B's time. If B takes x days, A takes (13x/8) days. Given (13x/8) - x = 15, solving gives x = 24 days. Since 25 > 24, Quantity I is greater.

Multiple choice
  1. Quantity I > Quantity II मात्रा I > मात्रा II

  2. Quantity I ≥ Quantity II मात्रा I ≥ मात्रा II

  3. Quantity II > Quantity I मात्रा II > मात्रा I

  4. Quantity II ≥ Quantity I मात्रा II ≥ मात्रा I

  5. Quantity I = Quantity II or Relation cannot be established मात्रा I = मात्रा II या संबंध स्थापित नहीं किया जा सकता है।

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Work is constant. (X-2)×2Y = (X+6)×Y gives 2XY-4Y = XY+6Y, so XY = 10Y, meaning X=10. This only fixes X=10; Y can be any positive value. Without a second equation, Y cannot be determined uniquely, so no relationship can be established.

Multiple choice
  1. Quantity II > Quantity मात्रा II > मात्रा I

  2. Quantity I ≥ Quantity II मात्रा I ≥ मात्रा II

  3. Quantity I > Quantity मात्रा I > मात्रा II

  4. Quantity I ≤ Quantity II मात्रा I ≤ मात्रा II

  5. Quantity I = Quantity II or relationship cannot be established मात्रा I = मात्रा II या कोई संबंध स्थापित नहीं किया जा सकता

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Quantity I: Ram takes 60 days alone. With efficiency ratio 3:2 (Ram:Shyam), combined efficiency = 3+2 = 5 units. Time = Total work (60*3 = 180 units) / 5 = 36 days. Quantity II: Ram does 1/5 work in 12 days, so full work in 60 days. Shyam does 1/3 work in 30 days, so full work in 90 days. Combined rate: 1/60 + 1/90 = 5/180 = 1/36, so 36 days. Both quantities equal 36 days.

Multiple choice
  1. Only I केवल I

  2. Only II केवल II

  3. Either I or II या तो I अथवा II

  4. Both together दोनों एक साथ

  5. Both together are not sufficient दोनों एक साथ भी पर्याप्त नहीं हैं

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Statement I: Ragini does 1/3 work at 80% efficiency in 24 days, so at full efficiency she would take 24 × 0.8 × 3 = 57.6 days alone. Statement II: Supriya is 40% more efficient, so her rate = 1.4 × (1/57.6) work/day. Combined they complete work in alternate days. Day 1 (Ragini): 1/57.6 work. Day 2 (Supriya): 1.4/57.6 work. Every 2 days: 2.4/57.6 = 1/24 work. Total = 48 days. Both statements needed.

Multiple choice
  1. 20th day 20 वें दिन

  2. 21st day 21 वें दिन

  3. 22nd day 22 वें दिन

  4. None of the above इनमे से कोई नहीं

  5. Cannot be determined निर्धारित नहीं किया जा सकता है

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let m,w,c be work per day by 1 man, 1 woman, 1 child. From given: 12m+16w=1/26, 10w+18c=1/20, 8m+16c=1/25. Solving the system gives m=1/5200, w=1/5200, c=1/5200 (each does equal work). Total work = 1. On day 1, work done = 3/5200. Each subsequent day adds 3 more workers, so day n completes work at rate 3n/5200. Work completed by day n = sum of 3i/5200 for i=1 to n = 3n(n+1)/(2×5200). Setting this equal to 1 and solving gives n=20.88, so work completes on day 21.

Multiple choice
  1. 5 (2/7)

  2. 7 (1/3)

  3. 6 (2/3)

  4. 4 (1/3)

  5. None of these /इनमें से को नहीं

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Kunal's rate: 1/10 work per day. Manish's rate: 1/20 work per day. Combined rate: 3/20 per day. In 3 days together: 3 × 3/20 = 9/20 work done. Remaining: 11/20. Manish does this alone at 1/20 per day, taking 11 days. Total days for Manish: 3 (together) + 11 (alone) = 14 days. If both worked together: 1/(3/20) = 20/3 = 6 2/3 days. Manish worked 14 - 6 2/3 = 7 1/3 days more. But wait - the question asks how many days Manish worked alone MORE THAN the days required when both work together. Manish alone for remaining work = 11 days. Together they'd take 6 2/3 days total. Difference: 11 - 6 2/3 = 4 1/3 days. This matches option D.

Multiple choice
  1. Quantity I > Quantity II मात्रा I > मात्रा II

  2. Quantity I ≥ Quantity II मात्रा I ≥ मात्रा II

  3. Quantity I < Quantity II मात्रा I < मात्रा II

  4. Quantity I ≤ Quantity II मात्रा I ≤ मात्रा II

  5. Quantity I = Quantity II or relation can’t be established मात्रा I = मात्रा II या सम्बन्ध स्थापित नही किया जा सकता|

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

QI: B takes 20 days alone. C is twice efficient, so C takes 20/2 = 10 days. A takes 10+2 = 12 days. Together: 1/12 + 1/20 + 1/10 = 5/60 + 3/60 + 6/60 = 14/60 = 7/30 work/day. For 7 works: Time = 7 × 30/7 = 30 days. QII: A(24), B(30), C(40). A+B work for 6 days: 6×(1/24+1/30) = 6×(5/120+4/120) = 6×9/120 = 54/120 = 9/20 work. Remaining = 11/20. Then A+B+C together: 1/24+1/30+1/40 = 5/120+4/120+3/120 = 12/120 = 1/10. Time for remaining = (11/20) / (1/10) = 11/2 = 5.5 days. Total = 6 + 5.5 = 11.5 days. Comparing: QI = 30 days, QII = 11.5 days. QI > QII, so A is correct.

Multiple choice
  1. 23 days 23 दिन

  2. 32 days 32 दिन

  3. 30 days 30 दिन

  4. 26 days 26 दिन

  5. 25 days 25 दिन

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let one woman's efficiency = 1 unit/day. Total work = 30 × 20 = 600 units. In 5 days, 30 women complete 150 units. Remaining 450 units must be done in 15 days by 30 women + 4 men (12 units equivalent = 42 total). Actual rate = 450/15 = 30 units/day. Without 4 men, rate = 30 units/day, so 600 units would take 600/30 = 20 more days after day 5, totaling 26 days.