Time and Work Questions

Multiple choice
  1. $8$ days
  2. $5$ days
  3. $7$ days
  4. $9$ days
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A's rate = 1/12, B's rate = 1/16. Combined rate = 1/12 + 1/16 = 7/48. In 3 days, they do 3 * (7/48) = 21/48 = 7/16 of the work. Remaining work = 1 - 7/16 = 9/16. B takes (9/16) / (1/16) = 9 days to finish.

Multiple choice
  1. $60$ days
  2. $15$ days
  3. $6$ days
  4. $51$ days
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let M be the work of a man and C be the work of a child per day. From the problem, 2M + 7C = 1/4 and 4M + 4C = 1/3. Solving this system gives M = 1/15, meaning one man completes the work in 15 days.

Multiple choice
  1. $8$ days
  2. $12$ days
  3. $6$ days
  4. $11$ days
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

If 1 man, 2 women, or 3 boys take 22 days, their daily work rates are 1/22, 1/44, and 1/66 of the total work respectively. The combined rate of 1 man, 1 woman, and 1 boy is (1/22 + 1/44 + 1/66) = (6+3+2)/132 = 11/132 = 1/12. Thus, they complete the work in 12 days.

Multiple choice
  1. $10$ days
  2. $11$ days
  3. $15$ days
  4. $20$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A+B = 1/12, A = 1/20. So B = 1/12 - 1/20 = (5-3)/60 = 2/60 = 1/30. If B works half-time, his rate is 1/60. Combined rate = 1/20 + 1/60 = 4/60 = 1/15. Time taken = 15 days.

Multiple choice
  1. $18$ days
  2. $30$ days
  3. $24$ days
  4. $21$ days
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let M be the work of a man and B be the work of a boy per day. From the equations 14(2M + 7B) = W and 11(3M + 8B) = W, we find 28M + 98B = 33M + 88B, which simplifies to 5M = 10B or M = 2B. Substituting M = 2B into the first equation, 14(4B + 7B) = 154B = W. For 8M + 6B, we have 8(2B) + 6B = 22B. The time required for 3W is (3 * 154B) / 22B = 21 days.

Multiple choice
  1. $10$ days
  2. $12$ days
  3. $15$ days
  4. $8$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A and B's rates be a and b. 1/a + 1/b = 1/5. If A is 2a and B is b/2, 1/(2a) + 1/(b/2) = 1/4, which is 1/(2a) + 2/b = 1/4. Solving the system: 1/a + 1/b = 1/5 and 1/(2a) + 2/b = 1/4. Multiply first by 2: 2/a + 2/b = 2/5. Subtract second: 1.5/a = 2/5 - 1/4 = 3/20. So 1/a = (3/20) * (2/3) = 1/10. A takes 10 days.

Multiple choice
  1. 13$\dfrac{1}{2}$ days
  2. $13$ days
  3. 12 $\dfrac{1}{2}$days
  4. $14$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let M be men's daily work and B be boys' daily work. 10(2M + 3B) = 1, so 2M + 3B = 0.1. 8(3M + 2B) = 1, so 3M + 2B = 0.125. Solving the system: M = 0.0375, B = 0.00833. For 2M + 1B, work per day = 2(0.0375) + 0.00833 = 0.0833. Days = 1 / 0.0833 = 12.5 days.

Multiple choice
  1. 15

  2. 18

  3. 12.5

  4. 16

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let M be the work of a man and B be the work of a boy per day. 10(2M + 3B) = 1, so 20M + 30B = 1. 8(3M + 2B) = 1, so 24M + 16B = 1. Solving the system: 80M + 120B = 4 and 180M + 120B = 7.5. Subtracting gives 100M = 3.5, M = 0.035. Then 30B = 1 - 20(0.035) = 0.3, B = 0.01. 2M + 1B = 2(0.035) + 0.01 = 0.08. Time = 1 / 0.08 = 12.5 days.

Multiple choice
  1. $25$
  2. $27$
  3. $29$
  4. $33$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let x be the number of men. Total work = 16 * 14 = 224 man-days. Work done in first 5 days = 5x. Remaining work = 224 - 5x. After 7 men leave, x-7 men work for 3 days. Then (x-7)/2 men work for 5 days. Setting up the equation: 5x + 3(x-7) + 5((x-7)/2) = 224. Solving this yields x = 25.

Multiple choice
  1. $22.5$ days
  2. $22$ days
  3. $24.5$ days
  4. $24$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Efficiency ratio A:B = 3:1. Time ratio A:B = 1:3. Let A take x days, B takes 3x days. 3x - x = 60 -> 2x = 60 -> x = 30. A takes 30 days, B takes 90 days. Combined rate = 1/30 + 1/90 = 4/90 = 2/45. Time = 45/2 = 22.5 days.