Time and Work Questions

Multiple choice
  1. $24\ days$
  2. $25\ days$
  3. $30\ days$
  4. $35\ days$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A does 1/80 per day. In 10 days, A does 10/80 = 1/8. Remaining work = 7/8. B does 7/8 in 42 days, so B does 1/48 per day. Together, they do 1/80 + 1/48 = (3+5)/240 = 8/240 = 1/30. They finish in 30 days.

Multiple choice
  1. Kathy will complete the repairs within $108$ days
  2. Kathy starts each week with $108$ phones to fix
  3. Kathy repairs phones at a rate of $108$ per hour
  4. Kathy repairs phones at a rate of $108$ per day
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

The equation P = 108 - 23d represents a linear function where 108 is the y-intercept, representing the starting value when d=0.

Multiple choice
  1. $\displaystyle \frac{y}{x+y}$ days
  2. $\displaystyle \frac{x}{x+y}$ days
  3. $\displaystyle \frac{xy}{x+y}$ days
  4. $\displaystyle \frac{xy}{x-y}$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate is 1/x and B's rate is 1/y. Combined rate is (1/x + 1/y) = (x+y)/xy. The time taken is the reciprocal of the combined rate, which is xy/(x+y).

Multiple choice
  1. $\dfrac35$
  2. $\dfrac37$
  3. $\dfrac34$
  4. $\dfrac14$
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Initial work = 25 * 12 = 300 man-days. With 20 workers, days required = 300 / 20 = 15 days. The increase in days is 15 - 12 = 3 days. The fraction of increase is 3/12 = 1/4.

Multiple choice
  1. 52

  2. 104

  3. 64

  4. 65

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let the daily work rates of A and B be 8x and 5x respectively, making their combined rate 13x. Since they complete the work together in 40 days, the total work is 13x * 40 = 520x. If A works alone, the time required is 520x / 8x = 65 days.

Multiple choice
  1. $8$ days
  2. $10$ days
  3. $6$ days
  4. $2$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

1/A + 1/B = 1/8, 1/B + 1/C = 1/12, 1/A + 1/B + 1/C = 1/6. (1/A + 1/B + 1/C) - (1/B + 1/C) = 1/A = 1/6 - 1/12 = 1/12. (1/A + 1/B + 1/C) - (1/A + 1/B) = 1/C = 1/6 - 1/8 = 1/24. 1/A + 1/C = 1/12 + 1/24 = 3/24 = 1/8. So A and C take 8 days.