Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
$24\ days$
-
$25\ days$
-
$30\ days$
-
$35\ days$
C
Correct answer
Explanation
A does 1/80 per day. In 10 days, A does 10/80 = 1/8. Remaining work = 7/8. B does 7/8 in 42 days, so B does 1/48 per day. Together, they do 1/80 + 1/48 = (3+5)/240 = 8/240 = 1/30. They finish in 30 days.
-
$60$ days
-
$45$ days
-
$54$ days
-
$48$ days
D
Correct answer
Explanation
Work = Men * Days. 12 * 16 = 4 * D. D = (12 * 16) / 4 = 3 * 16 = 48.
C
Correct answer
Explanation
Carpenter A makes 8/6 chairs/day, B makes 8/7, C makes 8/8. Total per day = 8/6 + 8/7 + 1 = (28+24+21)/21 = 73/21. In 21 days, total = (73/21) * 21 = 73.
A
Correct answer
Explanation
Using the work formula M1*D1 = M2*D2: 20 * 7 = M2 * 35. M2 = 140 / 35 = 4.
-
Kathy will complete the repairs within $108$ days
-
Kathy starts each week with $108$ phones to fix
-
Kathy repairs phones at a rate of $108$ per hour
-
Kathy repairs phones at a rate of $108$ per day
B
Correct answer
Explanation
The equation P = 108 - 23d represents a linear function where 108 is the y-intercept, representing the starting value when d=0.
-
10 days
-
12 days
-
14 days
-
15 days
A
Correct answer
Explanation
2(A+B+C) = 1/12 + 1/15 + 1/20 = (5+4+3)/60 = 12/60 = 1/5. A+B+C = 1/10. Days = 10.
-
$\displaystyle \frac{y}{x+y}$ days
-
$\displaystyle \frac{x}{x+y}$ days
-
$\displaystyle \frac{xy}{x+y}$ days
-
$\displaystyle \frac{xy}{x-y}$ days
C
Correct answer
Explanation
A's rate is 1/x and B's rate is 1/y. Combined rate is (1/x + 1/y) = (x+y)/xy. The time taken is the reciprocal of the combined rate, which is xy/(x+y).
-
$\dfrac35$
-
$\dfrac37$
-
$\dfrac34$
-
$\dfrac14$
D
Correct answer
Explanation
Initial work = 25 * 12 = 300 man-days. With 20 workers, days required = 300 / 20 = 15 days. The increase in days is 15 - 12 = 3 days. The fraction of increase is 3/12 = 1/4.
-
$10$ days
-
$12$ days
-
$15$ days
-
$20$ days
-
$6$ days
-
$4$ days
-
$8$ days
-
$2$ days
B
Correct answer
Explanation
Work rates are 1/12, 1/15, and 1/10. Combined rate is (5+4+6)/60 = 15/60 = 1/4. Time taken = 4 days.
D
Correct answer
Explanation
Let the daily work rates of A and B be 8x and 5x respectively, making their combined rate 13x. Since they complete the work together in 40 days, the total work is 13x * 40 = 520x. If A works alone, the time required is 520x / 8x = 65 days.
D
Correct answer
Explanation
Work = Men * Days. 36 * 18 = 27 * D. D = (36 * 18) / 27 = 4 * 6 = 24.
-
$8$ days
-
$10$ days
-
$6$ days
-
$2$ days
A
Correct answer
Explanation
1/A + 1/B = 1/8, 1/B + 1/C = 1/12, 1/A + 1/B + 1/C = 1/6. (1/A + 1/B + 1/C) - (1/B + 1/C) = 1/A = 1/6 - 1/12 = 1/12. (1/A + 1/B + 1/C) - (1/A + 1/B) = 1/C = 1/6 - 1/8 = 1/24. 1/A + 1/C = 1/12 + 1/24 = 3/24 = 1/8. So A and C take 8 days.
B
Correct answer
Explanation
This is an inverse proportion problem. 20 persons * 7 days = x persons * 28 days. x = (20 * 7) / 28 = 140 / 28 = 5.
-
$1380$
-
$1320$
-
$1260$
-
$920$
A
Correct answer
Explanation
Using the formula (M1*D1*H1)/W1 = (M2*D2*H2)/W2: (12*240*6)/460 = (18*360*8)/W2. 17280/460 = 51840/W2. W2 = (51840 * 460) / 17280 = 3 * 460 = 1380.