Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
C
Correct answer
Explanation
Use M1*D1*H1 = M2*D2*H2. 12 * 18 * 8 = 16 * 9 * H2. 1728 = 144 * H2. H2 = 1728 / 144 = 12.
-
15 days
-
18 days
-
16 days
-
20 days
C
Correct answer
Explanation
If A+B do the work in 8 days and B in 12 days, A's rate is 1/8 - 1/12 = 1/24 of the work per day. B works for 4 days, completing 4/12 = 1/3 of the work, leaving 2/3 of the work for A. A completes the remaining 2/3 at a rate of 1/24, taking (2/3) * 24 = 16 days.
-
4 days
-
5 days
-
8 days
-
10 days
C
Correct answer
Explanation
A cultivates 2/5 of the land in 6 days, so A's rate is (2/5)/6 = 1/15 land per day. B cultivates 1/3 of the land in 10 days, so B's rate is (1/3)/10 = 1/30 land per day. Together, their rate is 1/15 + 1/30 = 3/30 = 1/10 land per day; to cultivate 4/5 of the land, they need (4/5) / (1/10) = 8 days.
-
18 days
-
24 days
-
30 days
-
36 days
A
Correct answer
Explanation
Combined rates: A+B=1/30, B+C=1/24, C+A=1/20. Summing these gives 2(A+B+C) = 1/30+1/24+1/20 = 15/120 = 1/8, so A+B+C = 1/16. In 10 days, they do 10/16 = 5/8 of the work. Remaining work is 3/8. A's rate is (A+B+C) - (B+C) = 1/16 - 1/24 = 1/48. Time for A = (3/8) / (1/48) = 18 days.
-
7 days
-
8 days
-
9 days
-
10 days
B
Correct answer
Explanation
A = 1/11, B = 1/20, C = 1/55. Day 1: A works = 1/11. Day 2: A+B+C = 1/11 + 1/20 + 1/55 = (20 + 11 + 4)/220 = 35/220 = 7/44. Cycle (2 days) = 1/11 + 7/44 = 11/44 = 1/4. In 8 days (4 cycles), work = 4 * 1/4 = 1. Work done in 8 days.
-
120 days
-
20 days
-
80 days
-
36 days
-
$45$ days
-
$50$ days
-
$55.5$ days
-
$56.66$ days
-
None of these
D
Correct answer
Explanation
Work = 40 * 40 = 1600 man-days. Days 1-10: 40 men * 10 days = 400. Days 11-20: 35 men * 10 days = 350. Days 21-30: 30 men * 10 days = 300. Days 31-40: 25 men * 10 days = 250. Days 41-50: 20 men * 10 days = 200. Total so far = 1500. Remaining work = 100. Days 51 onwards: 15 men. 100/15 = 6.66 days. Total = 50 + 6.66 = 56.66.
B
Correct answer
Explanation
M does 1/21 per day, N does 1/42 per day. In a 2-day cycle, they do 1/21 + 1/42 = 3/42 = 1/14 of the work. To complete 1 whole work, they need 14 cycles of 2 days each, totaling 28 days.
-
$30\ days$
-
$32\ days$
-
$10\ days$
-
$40\ days$
D
Correct answer
Explanation
X+Y = 1/30 work/day. In 6 days, they do 6/30 = 1/5 work. Remaining = 4/5 work. Y does 4/5 work in 32 days, so Y's rate = (4/5) / 32 = 1/40 work/day. Y takes 40 days to finish the work.
-
$80$ days
-
$90$ days
-
$100$ days
-
$120$ days
C
Correct answer
Explanation
A, B, and C together complete 1/40 of the work per day. In 16 days they complete 2/5, leaving 3/5 for B and C, which they finish in 40 days, so their rate is 3/200 per day. A's rate is therefore 1/40 - 3/200 = 1/100, so A alone needs 100 days.
D
Correct answer
Explanation
Let A and B's work rates be a and b. Given 30(a+b) = 1 (total work). They worked together for 20 days: 20(a+b) = 2/3 of work. Remaining work 1/3 was done by A in 20 days, so A's rate is (1/3)/20 = 1/60. Since a+b = 1/30, then b = 1/30 - 1/60 = 1/60. Thus, B takes 60 days.
B
Correct answer
Explanation
Let Tinu's time be x days and father's time be x-9 days. Their combined rate is 1/x + 1/(x-9) = 1/6. Solving this quadratic equation x^2 - 21x + 54 = 0 gives x=18 or x=3. Since x must be greater than 9, Tinu takes 18 days.
-
$10$ days
-
$20$ days
-
$30$ days
-
$40$ days
C
Correct answer
Explanation
Let Ganesh take x days, John takes x-10 days. Together: 1/x + 1/(x-10) = 1/12. Solving x^2 - 34x + 120 = 0 gives (x-30)(x-4) = 0. Since x > 10, x = 30.
-
$3$ days
-
$5$ days
-
$4$ days
-
None of these
A
Correct answer
Explanation
Let Dominic take x days. Kim takes x-3 days. 1/x + 1/(x-3) = 1/2. 2(x-3 + x) = x(x-3). 4x - 6 = x^2 - 3x. x^2 - 7x + 6 = 0. (x-6)(x-1) = 0. x=6. Kim takes 6-3 = 3 days.
-
$24\ days$
-
$22\ days$
-
$20\ days$
-
$26\ days$
A
Correct answer
Explanation
Let Manoj take x days, Mohan takes x - 16 days. Together: 1/(x-16) + 1/x = 1/15. Solving this quadratic: x^2 - 46x + 240 = 0. Factors are (x-40)(x-6) = 0. Since x > 16, x = 40. Mohan = 40 - 16 = 24 days.