Time and Work Questions

Multiple choice
  1. $23$ days
  2. $37$ days
  3. $37\cfrac{1}{2}$
  4. $40$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A does 80% in 20 days, so A's rate is 4% per day. Remaining 20% is done by A and B in 3 days, so (A+B)'s rate is 20/3 = 6.66% per day. B's rate = 6.66 - 4 = 2.66% per day. Time for B = 100 / 2.66 = 37.5 days.

Multiple choice
  1. $I$ alone sufficient while $II$ alone not sufficient to answer
  2. $II$ alone sufficient while $I$ alone not sufficient to answer
  3. Either $I$ or $II$ alone sufficient to answer
  4. Both $I$ and $II$ are not sufficient to answer
  5. Both $I$ and $II$ are necessary to answer
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Statement I: A+B take 7 days. If they work 5 days, they finish 5/7 of the work. A finishes the remaining 2/7 alone. This is sufficient. Statement II: Does not provide enough info to isolate A's work.

Multiple choice
  1. $5$ days
  2. $6$ days
  3. $10$ days
  4. $10\cfrac{1}{2}$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's work rate is 1/24, B's is 1/9, C's is 1/12. B and C work for 3 days, completing 3 * (1/9 + 1/12) = 3 * (4/36 + 3/36) = 3 * (7/36) = 7/12 of the work. Remaining work is 1 - 7/12 = 5/12. A completes this in (5/12) / (1/24) = 5/12 * 24 = 10 days.

Multiple choice
  1. Any two of the three

  2. $I$ and $II$ only
  3. $II$ and $III$ only
  4. $I$ and $III$ only
  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let M be men's rate, W be women's rate. I: 10M = 1/6. II: 10M + 10W = 1/(24/7) = 7/24. III: 10M*3 + 10W*4 = 1. Any two of these equations allow solving for M and W, thus finding the time for 10 women (1/W).

Multiple choice
  1. $13\cfrac{1}{3}$ days
  2. $15$ days
  3. $20$ days
  4. $26$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

X does 1/40 of work per day. In 8 days, X does 8/40 = 1/5 of the work. Remaining work = 4/5. Y finishes 4/5 in 16 days, so Y does (4/5)/16 = 1/20 of the work per day. Together, they do 1/40 + 1/20 = 3/40 of the work per day. Time taken = 40/3 = 13 1/3 days.

Multiple choice
  1. $I$ only
  2. $II$ and $III$ only
  3. $III$ only
  4. $I$ and $III$ only
  5. Any one of the three

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

All three statements provide enough information to calculate the total work capacity and thus the number of workers required for 10 days. I: 20% in 8 days by 8 workers -> 100% in 40 days by 8 workers -> 10 days by 32 workers. II: 20 workers in 16 days -> 10 days by 32 workers. III: 1/8 in 5 days by 8 workers -> 100% in 40 days by 8 workers -> 10 days by 32 workers.

Multiple choice
  1. $I$ only
  2. $II$ only
  3. $III$ only
  4. $I$ or $II$ or $III$
  5. $II$ or $III$ only
Reveal answer Fill a bubble to check yourself
D Correct answer
Multiple choice
  1. $14$ days
  2. $6$ days
  3. $8$ days
  4. $10$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's work rate is 1/20, B's is 1/15, and C's is 1/12. On day 1, A and B work together (1/20 + 1/15 = 7/60); on day 2, A and C work together (1/20 + 1/12 = 8/60). In 2 days, they complete 15/60 = 1/4 of the work, so the total work takes 8 days.

Multiple choice
  1. $\dfrac {3}{4}$ days
  2. $1\dfrac {1}{2}days$
  3. $3\ days$
  4. $7\ days$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A's rate = 1 / (20/3) = 3/20 work/day. B's rate = 1/5 = 4/20 work/day. Combined rate = 7/20 work/day. Work done in 2 days = 2 * (7/20) = 14/20 = 7/10. Remaining work = 3/10. B finishes 3/10 at rate 1/5: (3/10) / (1/5) = 15/10 = 1.5 days.