Time and Work Questions

Multiple choice
  1. $\displaystyle 30$ days
  2. $\displaystyle 45$ days
  3. $\displaystyle 22\frac{1}{2}$ days
  4. $\displaystyle 17\frac{1}{2}$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let B take x days, A takes x/3 days. x - x/3 = 60, so 2x/3 = 60, x = 90. A takes 30 days, B takes 90 days. Together: (30*90)/(30+90) = 2700/120 = 22.5 days.

Multiple choice
  1. $18$ days and $36$ days
  2. $22$ days and $18$ days
  3. $11$ days and $13$ days
  4. $17$ days and $16$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let M be work of one man, B be work of one boy. 4(2M + 5B) = 1, so 8M + 20B = 1. 3(3M + 6B) = 1, so 9M + 18B = 1. Solving the system: 72M + 180B = 9; 72M + 144B = 8. Subtracting: 36B = 1, so B = 1/36. 8M + 20/36 = 1, 8M = 16/36, M = 2/36 = 1/18. Man takes 18 days, boy takes 36 days.

Multiple choice
  1. $48$ days
  2. $36$ days
  3. $24$ days
  4. $12$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work done by X in 1 day = 1/24. Work done by Y in 1 day = 1/16. Work done by X+Y+Z in 1 day = 1/8. Work done by Z = 1/8 - (1/24 + 1/16) = 1/8 - (2/48 + 3/48) = 6/48 - 5/48 = 1/48. Z takes 48 days.

Multiple choice
  1. $24$th day
  2. $25$th day
  3. $26$th day
  4. $27$th day
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A does 1/20 per day, B does 1/40 per day. In 2 days, they do 1/20 + 1/40 = 3/40. In 24 days (12 cycles), they do 12 * 3/40 = 36/40 = 9/10. On the 25th day, A does 1/20 (2/40), total 38/40. On the 26th day, B does 1/40, total 39/40. On the 27th day, A finishes the remaining 1/40.

Multiple choice
  1. $4$
  2. $5$
  3. $7$
  4. $8$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let total work be 60 units. Rates: A=6, B=5, C=4. Let total days be T. A worked for T-5 days, B for T-2 days, C for T days. 6(T-5) + 5(T-2) + 4T = 60. 6T-30 + 5T-10 + 4T = 60. 15T = 100. T = 6.66. Checking the logic: If T=7, A works 2 days, B works 5 days, C works 7 days. 12+25+28 = 65. Close. Re-reading: A left 5 days before completion, B left 2 days after A (so 3 days before completion). 6(T-5) + 5(T-3) + 4T = 60. 15T = 60+30+15 = 105. T = 7.

Multiple choice
  1. $125$ days
  2. $150$ days
  3. $90$ days
  4. $225$ days
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

1 man = 1/100 work/day. 10 men = 10/100 = 1/10 work/day. 10 men + 15 women = 1/6 work/day. 15 women = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 work/day. 1 woman = 1/(15*15) = 1/225 work/day. So 1 woman finishes in 225 days.

Multiple choice
  1. $Rs. 200$
  2. $Rs. 160$
  3. $Rs. 150$
  4. $Rs. 170$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work rates: X=1/8, Y=1/12. Together in 3 days: 3(1/8 + 1/12 + Z) = 1. 3(5/24 + Z) = 1, so 5/24 + Z = 1/3, Z = 8/24 - 5/24 = 3/24 = 1/8. Since X and Z have the same rate (1/8), they do equal work. Total work is 3 days, X does 3/8 of the work. Share = (3/8) * 400 = 150.

Multiple choice
  1. $6$
  2. $8$
  3. $5$
  4. $4$
  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate is 1/12, B's is 1/15. A works alone for 3 days, completing 3/12 = 1/4 of the work. Remaining work is 3/4. Combined rate is 1/12 + 1/15 = 9/60 = 3/20. Time taken = (3/4) / (3/20) = 5 days.