Time and Work Questions

Multiple choice
  1. $120$ days
  2. $118$ days
  3. $115$ days
  4. $110$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A, B, C be the work done per day. A+B=1/10, B+C=1/15, C+A=1/20. Adding these: 2(A+B+C) = 1/10 + 1/15 + 1/20 = (6+4+3)/60 = 13/60. So A+B+C = 13/120. C = (A+B+C) - (A+B) = 13/120 - 1/10 = 1/120. C takes 120 days.

Multiple choice
  1. $7$
  2. $9$
  3. $5$
  4. $0$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A's rate be 1/21. Let B's rate be x. Together (A+B) = 1/12. So 1/21 + x = 1/12, x = 1/12 - 1/21 = (7-4)/84 = 3/84 = 1/28. If the task took 16 days, and A worked for (16-y) days, then (16-y)/21 + 16/28 = 1. (16-y)/21 + 4/7 = 1. (16-y)/21 = 3/7 = 9/21. 16-y = 9, so y = 7.

Multiple choice
  1. $ 3\dfrac{2}{3} $ Days
  2. $ 8 \dfrac{1}{3} $ Days
  3. $ 4 \dfrac{5}{3} $ Days
  4. $ 9 \dfrac{1}{3} $ Days
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let M be work of one man, B be work of one boy. 5(12M + 16B) = 1. 4(13M + 24B) = 1. 60M + 80B = 52M + 96B => 8M = 16B => M = 2B. Substitute: 5(12(2B) + 16B) = 5(40B) = 1 => 200B = 1. Work of 7M + 10B = 7(2B) + 10B = 24B. Time = 200B / 24B = 200/24 = 25/3 = 8 1/3 days.

Multiple choice
  1. $ 2\dfrac{5}{2} $
  2. $ 3\dfrac{7}{3} $
  3. $ 2\dfrac{6}{5} $
  4. $ 4\dfrac{1}{2} $
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A's rate = 1/20, B's rate = 1/15. Together they work for 6 days: 6 * (1/20 + 1/15) = 6 * (3/60 + 4/60) = 6 * 7/60 = 7/10. Remaining work = 3/10. B finishes this in (3/10) / (1/15) = 3/10 * 15 = 4.5 days, which is 4 1/2 days.

Multiple choice
  1. $24$ days
  2. $20$ days
  3. $14$ days
  4. $22$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let total work be 72 units. A+B = 3 units/day, B+C = 2 units/day, A+B+C = 4 units/day. C = (A+B+C) - (A+B) = 4 - 3 = 1 unit/day. A = (A+B+C) - (B+C) = 4 - 2 = 2 units/day. A+C = 2 + 1 = 3 units/day. Time = 72 / 3 = 24 days.

Multiple choice
  1. A in $20$ days, B in $150$ days, C in $20$ days
  2. A in $30$ days, B in $130$ days, C in $30$ days
  3. A in $60$ days, B in $120$ days, C in $40$ days
  4. A in $50$ days, B in $130$ days, C in $20$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let rates be a, b, c. 1/a + 1/b = 1/40, 1/b + 1/c = 1/30, 1/c + 1/a = 1/24. Summing gives 2(1/a + 1/b + 1/c) = 1/40 + 1/30 + 1/24 = (3+4+5)/120 = 12/120 = 1/10. So 1/a + 1/b + 1/c = 1/20. Then 1/c = 1/20 - 1/40 = 1/40 (C=40), 1/a = 1/20 - 1/30 = 1/60 (A=60), 1/b = 1/20 - 1/24 = 1/120 (B=120).

Multiple choice
  1. $12$ days
  2. $20$ days
  3. $44$ days
  4. $18$ days
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A does 1/4 work in 5 days, so A does 1 work in 20 days. B does 1/3 work in 10 days, so B does 1 work in 30 days. Combined rate = 1/20 + 1/30 = 3/60 + 2/60 = 5/60 = 1/12. They take 12 days.