Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
A
Correct answer
Explanation
Let B take x days, A takes x-5. 1/(x-5) + 1/x = 1/6. (x + x - 5) / (x^2 - 5x) = 1/6. 12x - 30 = x^2 - 5x. x^2 - 17x + 30 = 0. (x-15)(x-2) = 0. x=15. A takes 15-5 = 10 days.
-
$120$ days
-
$118$ days
-
$115$ days
-
$110$ days
A
Correct answer
Explanation
Let A, B, C be the work done per day. A+B=1/10, B+C=1/15, C+A=1/20. Adding these: 2(A+B+C) = 1/10 + 1/15 + 1/20 = (6+4+3)/60 = 13/60. So A+B+C = 13/120. C = (A+B+C) - (A+B) = 13/120 - 1/10 = 1/120. C takes 120 days.
-
$16$ days
-
$32$ dyas
-
$24$ days
-
$40$ days
-
$48$ days
C
Correct answer
Explanation
Let Ram take x days, then Shyam takes 2x days. (1/x) + (1/2x) = 1/16. (3/2x) = 1/16. 2x = 48, so x = 24.
A
Correct answer
Explanation
Let A's rate be 1/21. Let B's rate be x. Together (A+B) = 1/12. So 1/21 + x = 1/12, x = 1/12 - 1/21 = (7-4)/84 = 3/84 = 1/28. If the task took 16 days, and A worked for (16-y) days, then (16-y)/21 + 16/28 = 1. (16-y)/21 + 4/7 = 1. (16-y)/21 = 3/7 = 9/21. 16-y = 9, so y = 7.
A
Correct answer
Explanation
Total work = 40 workers * 10 days = 400 man-days. If the work must be done in 4 days, the number of workers needed is 400 / 4 = 100. Additional workers required = 100 - 40 = 60.
-
$112$ men
-
$128$ men
-
$140$ men
-
$133$ men
B
Correct answer
Explanation
M1*D1*H1 = M2*D2*H2. 90*24*8 = M2*18*7.5. 17280 = M2*135. M2 = 17280 / 135 = 128.
-
$ 3\dfrac{2}{3} $ Days
-
$ 8 \dfrac{1}{3} $ Days
-
$ 4 \dfrac{5}{3} $ Days
-
$ 9 \dfrac{1}{3} $ Days
B
Correct answer
Explanation
Let M be work of one man, B be work of one boy. 5(12M + 16B) = 1. 4(13M + 24B) = 1. 60M + 80B = 52M + 96B => 8M = 16B => M = 2B. Substitute: 5(12(2B) + 16B) = 5(40B) = 1 => 200B = 1. Work of 7M + 10B = 7(2B) + 10B = 24B. Time = 200B / 24B = 200/24 = 25/3 = 8 1/3 days.
B
Correct answer
Explanation
Let original number be x. Work = 10x. With 5 absent, work = 12(x-5). 10x = 12x - 60, so 2x = 60, x = 30.
-
$168$ days
-
$180$ days
-
$151$ days
-
$140$ days
A
Correct answer
Explanation
Let the work be 1 unit. A+B do 1/56 per day, and A+B+C do 1/42 per day. C's daily rate is (1/42) - (1/56) = (4-3)/168 = 1/168. Thus, C takes 168 days.
-
$ 2\dfrac{5}{2} $
-
$ 3\dfrac{7}{3} $
-
$ 2\dfrac{6}{5} $
-
$ 4\dfrac{1}{2} $
D
Correct answer
Explanation
A's rate = 1/20, B's rate = 1/15. Together they work for 6 days: 6 * (1/20 + 1/15) = 6 * (3/60 + 4/60) = 6 * 7/60 = 7/10. Remaining work = 3/10. B finishes this in (3/10) / (1/15) = 3/10 * 15 = 4.5 days, which is 4 1/2 days.
-
$ 3\cfrac{3}{7} $
-
$ 3\cfrac{3}{2} $
-
$ 5\cfrac{3}{5} $
-
$ 5\cfrac{3}{8} $
A
Correct answer
Explanation
The combined rate is 1/6 + 1/12 + 1/24 = (4+2+1)/24 = 7/24. Time taken = 24/7 = 3 and 3/7 days.
-
$24$ days
-
$20$ days
-
$14$ days
-
$22$ days
A
Correct answer
Explanation
Let total work be 72 units. A+B = 3 units/day, B+C = 2 units/day, A+B+C = 4 units/day. C = (A+B+C) - (A+B) = 4 - 3 = 1 unit/day. A = (A+B+C) - (B+C) = 4 - 2 = 2 units/day. A+C = 2 + 1 = 3 units/day. Time = 72 / 3 = 24 days.
-
$ 6\dfrac{2}{3} $
-
$ 15\dfrac{17}{19} $
-
$ 10\dfrac{10}{17} $
-
$ 11\dfrac{9}{4} $
C
Correct answer
Explanation
A = 1/10, B = 1/18, A+B+C = 1/4. C = 1/4 - (1/10 + 1/18) = 1/4 - (9/90 + 5/90) = 1/4 - 14/90 = 1/4 - 7/45 = (45 - 28) / 180 = 17/180. Time = 180/17 = 10 10/17 days.
-
A in $20$ days, B in $150$ days, C in $20$ days
-
A in $30$ days, B in $130$ days, C in $30$ days
-
A in $60$ days, B in $120$ days, C in $40$ days
-
A in $50$ days, B in $130$ days, C in $20$ days
C
Correct answer
Explanation
Let rates be a, b, c. 1/a + 1/b = 1/40, 1/b + 1/c = 1/30, 1/c + 1/a = 1/24. Summing gives 2(1/a + 1/b + 1/c) = 1/40 + 1/30 + 1/24 = (3+4+5)/120 = 12/120 = 1/10. So 1/a + 1/b + 1/c = 1/20. Then 1/c = 1/20 - 1/40 = 1/40 (C=40), 1/a = 1/20 - 1/30 = 1/60 (A=60), 1/b = 1/20 - 1/24 = 1/120 (B=120).
-
$12$ days
-
$20$ days
-
$44$ days
-
$18$ days
A
Correct answer
Explanation
A does 1/4 work in 5 days, so A does 1 work in 20 days. B does 1/3 work in 10 days, so B does 1 work in 30 days. Combined rate = 1/20 + 1/30 = 3/60 + 2/60 = 5/60 = 1/12. They take 12 days.