Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
B
Correct answer
Explanation
A's daily work is 1/6 and B's is 1/8. In 3 days, A does 3/6 = 1/2 and B does 3/8 of the work. Together they do 1/2 + 3/8 = 7/8 of the work, leaving 1/8 for C. Since C does 1/8 of the total work, C's share is 1/8 of 3200, which is 400.
-
$15$
-
$18$
-
$22$
-
None of these
A
Correct answer
Explanation
12 men = 4 days work, so 1 man = 48 days work. 15 women = 4 days work, so 1 woman = 60 days work. 6 men work for 2 days = 6 * 2 = 12 man-days. Total work = 48 man-days. Remaining work = 48 - 12 = 36 man-days. 36 man-days = 36 * (60/48) = 45 woman-days. To finish in 3 days, women needed = 45 / 3 = 15.
-
$\displaystyle \frac{20}{9}$ days
-
$\displaystyle \frac{11}{9}$ days
-
$3$ days
-
None of these
A
Correct answer
Explanation
A=3B, B=2C. So A=6C, B=2C. If B takes 10 days, the total work is 10 * B's rate. A+B+C rate = 6C + 2C + C = 9C. B's rate = 2C. Total work = 10 * 2C = 20C. Time = 20C / 9C = 20/9 days.
-
$12$ days
-
$4$ days
-
$2$ days
-
$\displaystyle 2\frac{2}{3}$ days
D
Correct answer
Explanation
A's rate is 1/8, B's rate is 1/4. Combined rate = 1/8 + 2/8 = 3/8. Time taken = 8/3 = 2 and 2/3 days.
-
$11$
-
$22$
-
$33$
-
None of these
A
Correct answer
Explanation
Total work = 22 * 17 = 374 man-days. Work done in 2 days = 22 * 2 = 44 man-days. Remaining work = 330 man-days. To finish in 10 days, we need 330 / 10 = 33 men. Additional men needed = 33 - 22 = 11.
-
$30$ days
-
$35 $ days
-
$40 $ days
-
None of these
A
Correct answer
Explanation
A does 1/2 work in 3/4 time. So A does 1 work in (3/4) * 2 = 3/2 time. A's rate = 2/3 of B's rate. A + B = 1/18. (2/3)B + B = 1/18. (5/3)B = 1/18. B = 3/90 = 1/30. B takes 30 days.
-
15 days
-
20 days
-
45 days
-
30 days
A
Correct answer
Explanation
A and B together complete 1/12 of the work per day, while A alone completes 1/20. Therefore, B completes 1/30 per day. If B works for half a day daily, B contributes 1/60 daily, and A plus this contribution completes 1/15 per day, requiring 15 days.
-
$\displaystyle \frac{4}{13}$
-
$\displaystyle \frac{1}{2}$
-
$\displaystyle \frac{1}{3}$
-
$\displaystyle \frac{6}{13}$
A
Correct answer
Explanation
A, B, and C complete work in 10, 15, and 20 days. Their rates are 1/10, 1/15, and 1/20. Total rate = 6/60 + 4/60 + 3/60 = 13/60. The fraction of work done by B is (Rate of B) / (Total Rate) = (1/15) / (13/60) = 4/13.
-
$2$ day
-
$4$ day
-
$5$ day
-
$6$ day
B
Correct answer
Explanation
Total work = 12 * 8 = 96 man-days. Work done in 3 days = 12 * 3 = 36 man-days. Remaining work = 96 - 36 = 60 man-days. New number of men = 12 + 3 = 15. Days to finish = 60 / 15 = 4 days.
-
$8$ days
-
$2$ days
-
$4$ days
-
$6$ days
D
Correct answer
Explanation
Anil's efficiency = 2 * Sunil's. Time taken is inversely proportional to efficiency. If Sunil takes T days, Anil takes T/2. T - T/2 = 3, so T/2 = 3, T = 6.
D
Correct answer
Explanation
Using the inverse proportion formula (M1*D1 = M2*D2), we have 12 * 21 = M2 * 15. Solving for M2 gives (12 * 21) / 15 = 252 / 15 = 16.8. Since the number of children must be an integer, 17 is the closest approximation.
A
Correct answer
Explanation
Work is constant. M1 * D1 = M2 * D2. 35 * 15 = M2 * 25. M2 = (35 * 15) / 25 = 35 * 0.6 = 21.
-
4 days
-
6 days
-
8 days
-
12 days
-
$15\dfrac{9}{3}$
-
$22\dfrac{4}{9}$
-
$15\dfrac{7}{4}$
-
$22\dfrac{1}{2}$
D
Correct answer
Explanation
Let B take x days, A takes x/3 days. x - x/3 = 60 => 2x/3 = 60 => x = 90. A takes 30 days, B takes 90 days. Together: (1/30 + 1/90)^-1 = (4/90)^-1 = 90/4 = 22.5 days.