Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
9.5 days
-
7.5 days
-
6 days
-
5 days
C
Correct answer
Explanation
Combined rate = 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6. Time taken = 6 days.
-
28 days
-
30 days
-
32 days
-
31 days
-
240/11 days
-
(21 + 7/8) days
-
24 days
-
15 days
B
Correct answer
Explanation
If A+B take T days, A takes T+25 and B takes T+9. 1/(T+25) + 1/(T+9) = 1/T. Solving gives T^2 = 225, so T = 15. A takes 40 days, B takes 24 days. Working alternate days: Day 1 (A): 1/40. Day 2 (A+B): 1/40 + 1/24 = 3/120 + 5/120 = 8/120 = 1/15. In 2 days, 1/40 + 1/15 = 11/120. In 20 days (10 cycles), 110/120 done. Remaining 10/120 = 1/12. Day 21 (A): 1/40. Remaining 1/12 - 1/40 = 7/120. Day 22 (A+B): 1/15. Remaining 7/120 - 8/120 (negative). Time is 21 + (7/120)/(8/120) = 21 + 7/8.
B
Correct answer
Explanation
16M+12W=1/20 work/day. 18W=1/40 work/day => 1W=1/720. 16M+12(1/720)=1/20 => 16M=1/20-1/60=2/60=1/30 => 1M=1/480. 12M+27W = 12/480 + 27/720 = 1/40 + 3/80 = 5/80 = 1/16. Time = 16 days.
-
6 days
-
8 days
-
11 days
-
15 days
-
16 days
B
Correct answer
Explanation
Karan rate = 1/20. Amit rate = -1/40. Kapil rate = 2 * (1/20) = 1/10. Combined rate = 1/20 + 1/10 - 1/40 = (2+4-1)/40 = 5/40 = 1/8. Time = 8 days.
-
12 days
-
15 days
-
16 days
-
18 days
-
None of these
B
Correct answer
Explanation
A's rate = 1/20, B's rate = 1/60. Combined rate = 1/20 + 1/60 = 3/60 + 1/60 = 4/60 = 1/15. Time taken = 15 days.
-
2 days
-
3 days
-
4 days
-
5 days
-
6 days
B
Correct answer
Explanation
This is an inverse proportion problem. 3 people * 4 days = 12 man-days of work. If 4 people do the same work, 12 / 4 = 3 days.
-
40 days
-
60 days
-
80 days
-
10 days
-
120 days
A
Correct answer
Explanation
A man does twice the work of a child. 50 children working 8 hours for 40 days = 16000 child-units. 40 men (equivalent to 80 children) working 5 hours a day for D days: 80 * 5 * D = 400D. Setting 400D = 16000 gives D = 40.
-
32 days
-
35 days
-
37 days
-
39 days
-
42 days
B
Correct answer
Explanation
Arun takes 3/4 time of Bipul to do half work. So Arun takes 3/2 time of Bipul to do full work. Let Bipul take x days, then Arun takes 1.5x days. 1/x + 1/1.5x = 1/21. (1.5 + 1) / 1.5x = 1/21. 2.5 / 1.5x = 1/21. 5 / 3x = 1/21. 3x = 105, so x = 35.
-
10 days
-
12 days
-
14 days
-
15 days
D
Correct answer
Explanation
Let work be 1 unit. (A+B+C) = 1/8, (A+B) = 1/10, (B+C) = 1/12. We want (A+C). Note that (A+B) + (B+C) = A + 2B + C = 1/10 + 1/12 = 11/60. Also (A+B+C) = 1/8. So B = (A+B+C) - (A+C) is not direct. Instead, (A+B+C) - (B+C) = A = 1/8 - 1/12 = 1/24. (A+B+C) - (A+B) = C = 1/8 - 1/10 = 1/40. A+C = 1/24 + 1/40 = (5+3)/120 = 8/120 = 1/15. Thus, they take 15 days.
-
32
-
24
-
16
-
12
-
None of these
B
Correct answer
Explanation
If 2 women take 16 days, 1 woman takes 32 days. 4 women take 32/4 = 8 days. In 4 days, 4 women do 4/8 = 1/2 of the work. The remaining 1/2 work is done by 12 children in 4 days, so 12 children do 1/8 of the work per day. 4 children do 1/24 of the work per day, taking 24 days.
-
16 days
-
14 days
-
12 days
-
21 days
-
18 days
A
Correct answer
Explanation
Using the formula (M1*D1*H1)/W1 = (M2*D2*H2)/W2, where 4 men = 10 boys, we find 1 man = 2.5 boys. The first work is 1 unit, the second is 3 units. 8 men and 5 boys equal 20 + 5 = 25 boys. Solving (10*12*10)/1 = (25*D2*9)/3 gives D2 = 16.
-
25%
-
30%
-
37.5%
-
50%
-
None of these
-
8 days
-
7.5 days
-
12 days
-
3 days
-
21 days
B
Correct answer
Explanation
If A takes 12 days, his rate is 1/12. B is 60% more efficient, so B's rate is 1.6 * (1/12) = 1.6/12 = 16/120 = 2/15. Time for B = 1 / (2/15) = 7.5 days.