Time and Work Questions

Multiple choice
  1. 42

  2. 23

  3. 32

  4. 27

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let M be the number of men. M * 28 = (M + 15) * (28 - 10). 28M = 18(M + 15). 28M = 18M + 270. 10M = 270. M = 27. The question asks for the number of men required to complete the work in the reduced time (18 days), which is M + 15 = 27 + 15 = 42.

Multiple choice
  1. 4 days

  2. 3 days

  3. 2 days

  4. 2.5 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Rates: Ram=1/8, Suraj=1/10, Rajesh=1/12. Combined rate = (15+12+10)/120 = 37/120. In 2 days, they do 2 * (37/120) = 37/60. Remaining work = 23/60. Suraj and Rajesh rate = 1/10 + 1/12 = 11/60. Time to finish = (23/60) / (11/60) = 23/11 = 2.09 days. Total time = 2 + 2.09 = 4.09 days, which is approximately 4 days.

Multiple choice
  1. 1:3

  2. 3:5

  3. 3:1

  4. 4:5

  5. 5:7

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let rates be P+Q=1/6, Q+R=1/15, P+R=3/20. Adding these gives 2(P+Q+R) = 1/6 + 1/15 + 3/20 = (10+4+9)/60 = 23/60, so P+Q+R = 23/120. R = (P+Q+R) - (P+Q) = 23/120 - 20/120 = 3/120 = 1/40 (40 days). Q = (P+Q+R) - (P+R) = 23/120 - 18/120 = 5/120 = 1/24 (24 days). Ratio Q:R = 24:40 = 3:5.

Multiple choice
  1. Only statement A

  2. Only statement B

  3. Any two of them

  4. Either A or B

  5. All three statements

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let B be the work rate of a boy and G be the work rate of a girl. A: 6B + 9G = 1/12. B: G = 1/468. C: 23B + 41G = 1/3. With B and G, we have two variables. Any two equations are sufficient to solve for B and G, which then allows calculating the time for 15B + 21G.

Multiple choice
  1. Only statements I and II

  2. Only statements I and III

  3. Only statement I and either statement II or statement III

  4. All three statements

  5. None of the statements

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Statement I gives the rate of 3M+5W. Statement II gives M=2.5W. Statement III gives 4M=10W, which is equivalent to 2M=5W. Statement I and either II or III allow us to express the total work in terms of one variable (e.g., all women) and solve for the time taken by 4M+10W.

Multiple choice
  1. 6 : 5

  2. 8 : 5

  3. 7 : 4

  4. 9 : 4

  5. 3 : 2

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

20 boys * 12 days = 240 boy-days. 15 men * 10 days = 150 man-days. Since the work is the same, 150 men = 240 boys, so 1 man = 240/150 boys = 1.6 boys = 8/5 boys. The ratio of efficiency (man to boy) is 8:5.

Multiple choice
  1. 3 days

  2. 2 days

  3. 4 days

  4. 5 days

  5. 1 day

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Efficiency: A = 2B, B = 2C, so A = 4C. Let C's rate be c. A=4c, B=2c, C=c. C+D take 4 days, so c + d = 1/4. D takes 6 days, so d = 1/6. c = 1/4 - 1/6 = 3/12 - 2/12 = 1/12. A's rate = 4c = 4/12 = 1/3. A takes 3 days.

Multiple choice
  1. 8 days

  2. 6 days

  3. 5 days

  4. 4 days

  5. 4.5 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work rates: Kyle 1/5, Megan 1/10, Chloe 1/15. Together: 6/30 + 3/30 + 2/30 = 11/30 per day. In 2 days, they do 22/30. Remaining work is 8/30. Chloe takes (8/30) / (1/15) = 4 days.

Multiple choice
  1. 6

  2. 8

  3. 9

  4. 12

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Chris's rate = 1/45, Robert's rate = 1/40. Robert works alone for 23 days, completing 23/40 of the work. Remaining work = 1 - 23/40 = 17/40. They worked together for time T: T(1/45 + 1/40) = 17/40. T(8/360 + 9/360) = 17/40 => T(17/360) = 17/40 => T = 9 days.

Multiple choice
  1. Rs. 385

  2. Rs. 400

  3. Rs. 550

  4. Rs. 785

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Jack's efficiency is 1/6, Jonny's is 1/8. Together they do (1/6 + 1/8) = 7/24 per day. In 3 days, they do 3 * (7/24) = 7/8 of the work. Rehan does 1/8 of the work. Payment is proportional to work: (1/8) * 3200 = 400.

Multiple choice
  1. 12 days

  2. 15 days

  3. 16 days

  4. 18 days

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Ronit's rate is 1/20, Alan's is 1/30, and Paul's is 1/60. In a 3-day cycle, Ronit works alone for 2 days (2/20) and with others on the 3rd day (1/20 + 1/30 + 1/60 = 6/60 = 1/10). Total work in 3 days is 2/20 + 1/10 = 1/10 + 1/10 = 1/5. Thus, 5 cycles of 3 days (15 days) complete the work.