Ram, Suraj and Rajesh are working on a short duration project. Ram alone can complete the project in 8 days, Suraj can complete the project in 10 days, while Rajesh can do it in 12 days. They start the work together, but after 2 days Ram leaves the work and the remaining project is completed by Suraj and Rajesh. How long (approximately) will the project take to get completed?