Time and Work Questions

Multiple choice
  1. 25th day

  2. 12th day

  3. 14th day

  4. 11th day

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let Y take x days; then X takes x/3 days. Given x - x/3 = 30, we find x = 45 days for Y and 15 days for X. Their combined rate is 1/45 + 1/15 = 4/45, meaning they finish in 45/4 = 11.25 days. They complete the work during the 12th day.

Multiple choice
  1. All together are necessary.

  2. Only A is sufficient.

  3. A and C together are sufficient.

  4. C and B together are sufficient.

  5. Either A or B is sufficient.

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A gives the ratio of efficiencies (Amit = 1.5 * Beth). C gives Beth's time. With both, we can find Amit's time and their combined rate. B is irrelevant.

Multiple choice
  1. 27 days

  2. 28 days

  3. 31 days

  4. 45 days

  5. 46 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let total days be x. Vibhu works for (x-13) days, Kashish works for x days. (x-13)/40 + x/56 = 1. Multiply by 280: 7(x-13) + 5x = 280. 7x - 91 + 5x = 280. 12x = 371. x = 30.91, which is approximately 31 days.

Multiple choice
  1. Rs. 307

  2. Rs. 73

  3. Rs. 75

  4. Rs. 267

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Their combined work rate is 1/4 + 1/8 + 1/12 = 11/24 of the task per day. In two days they complete 11/12 of the task, leaving Nirupama to complete 1/12. Her share is therefore Rs. 876/12 = Rs. 73.

Multiple choice
  1. 140/11 days

  2. 15 Days

  3. 20 Days

  4. 10 Days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A can complete the work in 20 days, and B can complete the entire work in 35 days. Their combined rate is 1/20 + 1/35 = 11/140 of the work per day, meaning they will take 10 days to complete 11/14 of the total work.

Multiple choice
  1. 8.5 days

  2. 7.5 days

  3. 9.5 days

  4. 8 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Aman rate = 1/20, Bhanu = 1/25, Cheenu = -1/50. Let t be the time Cheenu worked. (1/20 + 1/25 - 1/50)t + (1/20 + 1/25)(13-t) = 1. (5/100 + 4/100 - 2/100)t + (9/100)(13-t) = 1. 0.07t + 1.17 - 0.09t = 1. 0.17 = 0.02t. t = 8.5 days.

Multiple choice
  1. I and II are sufficient

  2. I and III are sufficient

  3. Any two of three are sufficient.

  4. II and III are sufficient.

  5. None

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let M and W be the work rates of one man and one woman. I: 10W = 1/6. II: 10M + 10W = 7/24. III: 30W + 40M = 1. Any two equations are sufficient to find M and W, and thus the time for 10 men.