Direction : Study the following questions carefully and choose the right answer. A contractor decided to complete a work in 90 days. He employed 250 men at the beginning and another 150 men after 60 days and completed the work in stipulated time. Had he not employed the additional men, what percent more time he would have taken to finish the work?