Time and Work Questions

Multiple choice
  1. 32

  2. 31

  3. 30

  4. 29

  5. 28

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = 8 * 21 = 168 man-days. 14 men work for 3 days = 42 man-days. Remaining work = 168 - 42 = 126 man-days. 9 women do this in 24 days, so 9 women's efficiency = 126/24 = 5.25 man-days per day. Total work for 9 women = 168 / 5.25 = 32 days.

Multiple choice
  1. 150

  2. 160

  3. 170

  4. 180

  5. 190

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Efficiency is inversely proportional to time. Pankaj's rate is 1/15, Bharti's is 1/12. Ratio of efficiencies = (1/15) : (1/12) = 4:5. Total parts = 9. Bharti's share of 90 is (5/9) * 90 = 50 per unit. For 20 days, they produce 20/15 + 20/12 = 4/3 + 5/3 = 3 units. Total earnings = 3 * 90 = 270. Bharti's share = (5/9) * 270 = 150.

Multiple choice
  1. 50%

  2. 75%

  3. 100%

  4. 150%

  5. 200%

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Ram does 40% in 12 days. Ram's rate = 40/12 = 10/3 % per day. Remaining 60% done by Ram and Ravi in 12 days. Combined rate = 60/12 = 5% per day. Ravi's rate = 5 - 10/3 = 5/3 % per day. Efficiency ratio Ram:Ravi = (10/3) : (5/3) = 2:1. Ram is 100% more efficient than Ravi.

Multiple choice
  1. 8(2/3) days

  2. 7(2/3) days

  3. 6(2/3) days

  4. 5(2/3) days

  5. 4(2/3) days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Using the formula (M1*D1*H1)/W1 = (M2*D2*H2)/W2. The efficiency condition implies 2 men * 2 hrs = 4 men * 1 hr, meaning they have equal efficiency. Thus, (30*10*4)/1 = (45*D2*8)/2. Solving for D2: 1200/1 = 360*D2/2, so 1200 = 180*D2, D2 = 1200/180 = 6.66 or 6(2/3) days.

Multiple choice
  1. 15 days

  2. 45 days

  3. 60 days

  4. 30 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A does 75% in 45 days, so 100% in 60 days. A's rate = 1/60 per day. Remaining work = 25%. A and B finish 25% in 5 days, so their combined rate = 0.25 / 5 = 1/20 per day. B's rate = (1/20) - (1/60) = 3/60 - 1/60 = 2/60 = 1/30. B takes 30 days.

Multiple choice
  1. 5 14

  2. 9 13

  3. 8 15

  4. 7 11

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Combined rate is 1/30 + 1/40 = 7/120 per day. In 8 days they complete 8 x 7/120 = 56/120 = 7/15 of the work, leaving 1 - 7/15 = 8/15. The option '8 15' represents the fraction 8/15 with a missing slash.

Multiple choice
  1. 3.2 days

  2. 4 days

  3. 4.8 days

  4. 9.6 days

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work rates: Aman=1/18, Simar=1/21, Karan=1/15. Combined rate = 1/18 + 1/21 + 1/15 = (35+30+42)/630 = 107/630. In 4 days, they do 4 * 107/630 = 428/630. Remaining work = 1 - 428/630 = 202/630. Karan's time = (202/630) / (1/15) = 202/630 * 15 = 202/42 = 4.809 days.

Multiple choice
  1. 3 days

  2. 6 days

  3. 7 days

  4. 12 days

  5. N/a

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Sumesh rate = 1/15 per day. Ramesh rate = 1/25 per day. Ramesh works for 15 days: 15/25 = 3/5 of the work done. Remaining work = 1 - 3/5 = 2/5. Sumesh completes 2/5 work at rate 1/15: (2/5) / (1/15) = (2/5) * 15 = 6 days.

Multiple choice
  1. Rs. 50

  2. Rs. 100

  3. Rs. 150

  4. Rs. 200

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's rate = 1/5, B's rate = 1/15. In 3 days, A does 3/5, B does 3/15 = 1/5. C does 1 - (3/5 + 1/5) = 1/5. Since they are paid in proportion to work, C gets 1/5 of 250 = 50.