Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
C
Correct answer
Explanation
Using M1D1 = M2D2: 30 * 36 = 18 * D2. D2 = (30 * 36) / 18 = 30 * 2 = 60.
-
4 days
-
8 days
-
9 days
-
12 days
B
Correct answer
Explanation
Use the formula (M1*D1*H1)/W1 = (M2*D2*H2)/W2. (6 * 8 * 5) / 750 = (4 * D2 * 8) / 800 => 240 / 750 = 32 * D2 / 800 => 0.32 = 0.04 * D2 => D2 = 8.
A
Correct answer
Explanation
Total work = 8 * 21 = 168 man-days. 14 men work for 3 days = 42 man-days. Remaining work = 168 - 42 = 126 man-days. 9 women do this in 24 days, so 9 women's efficiency = 126/24 = 5.25 man-days per day. Total work for 9 women = 168 / 5.25 = 32 days.
A
Correct answer
Explanation
Efficiency is inversely proportional to time. Pankaj's rate is 1/15, Bharti's is 1/12. Ratio of efficiencies = (1/15) : (1/12) = 4:5. Total parts = 9. Bharti's share of 90 is (5/9) * 90 = 50 per unit. For 20 days, they produce 20/15 + 20/12 = 4/3 + 5/3 = 3 units. Total earnings = 3 * 90 = 270. Bharti's share = (5/9) * 270 = 150.
C
Correct answer
Explanation
Ram does 40% in 12 days. Ram's rate = 40/12 = 10/3 % per day. Remaining 60% done by Ram and Ravi in 12 days. Combined rate = 60/12 = 5% per day. Ravi's rate = 5 - 10/3 = 5/3 % per day. Efficiency ratio Ram:Ravi = (10/3) : (5/3) = 2:1. Ram is 100% more efficient than Ravi.
D
Correct answer
Explanation
A's rate is 1/50 and B's rate is 1/40. In 10 days, they complete 10*(1/50 + 1/40) = 10*(9/200) = 9/20 of the work. The remaining 11/20 of the work is done by B at a rate of 1/40, taking (11/20) * 40 = 22 days.
-
8(2/3) days
-
7(2/3) days
-
6(2/3) days
-
5(2/3) days
-
4(2/3) days
C
Correct answer
Explanation
Using the formula (M1*D1*H1)/W1 = (M2*D2*H2)/W2. The efficiency condition implies 2 men * 2 hrs = 4 men * 1 hr, meaning they have equal efficiency. Thus, (30*10*4)/1 = (45*D2*8)/2. Solving for D2: 1200/1 = 360*D2/2, so 1200 = 180*D2, D2 = 1200/180 = 6.66 or 6(2/3) days.
-
15 days
-
45 days
-
60 days
-
30 days
D
Correct answer
Explanation
A does 75% in 45 days, so 100% in 60 days. A's rate = 1/60 per day. Remaining work = 25%. A and B finish 25% in 5 days, so their combined rate = 0.25 / 5 = 1/20 per day. B's rate = (1/20) - (1/60) = 3/60 - 1/60 = 2/60 = 1/30. B takes 30 days.
-
5 14
-
9 13
-
8 15
-
7 11
-
None of these
C
Correct answer
Explanation
Combined rate is 1/30 + 1/40 = 7/120 per day. In 8 days they complete 8 x 7/120 = 56/120 = 7/15 of the work, leaving 1 - 7/15 = 8/15. The option '8 15' represents the fraction 8/15 with a missing slash.
-
3.2 days
-
4 days
-
4.8 days
-
9.6 days
-
None of these
C
Correct answer
Explanation
Work rates: Aman=1/18, Simar=1/21, Karan=1/15. Combined rate = 1/18 + 1/21 + 1/15 = (35+30+42)/630 = 107/630. In 4 days, they do 4 * 107/630 = 428/630. Remaining work = 1 - 428/630 = 202/630. Karan's time = (202/630) / (1/15) = 202/630 * 15 = 202/42 = 4.809 days.
D
Correct answer
Explanation
If A is twice as good as B, their efficiency ratio is 2:1. Together they do 3 units of work per day. Total work = 3 * 16 = 48 units. A alone takes 48 / 2 = 24 days.
-
3 days
-
6 days
-
7 days
-
12 days
-
N/a
B
Correct answer
Explanation
Sumesh rate = 1/15 per day. Ramesh rate = 1/25 per day. Ramesh works for 15 days: 15/25 = 3/5 of the work done. Remaining work = 1 - 3/5 = 2/5. Sumesh completes 2/5 work at rate 1/15: (2/5) / (1/15) = (2/5) * 15 = 6 days.
-
Rs. 1,600
-
Rs. 800
-
Rs. 600
-
Rs. 400
-
na
B
Correct answer
Explanation
X's rate = 1/12, Y's rate = 1/16. Together in 6 days: 6 * (1/12 + 1/16) = 6 * (7/48) = 7/8 of the work. Z did 1/8 of the work. Payment for Z = (1/8) * 6400 = 800.
-
Rs. 50
-
Rs. 100
-
Rs. 150
-
Rs. 200
A
Correct answer
Explanation
A's rate = 1/5, B's rate = 1/15. In 3 days, A does 3/5, B does 3/15 = 1/5. C does 1 - (3/5 + 1/5) = 1/5. Since they are paid in proportion to work, C gets 1/5 of 250 = 50.