(a) 16 days
-
(b) 12 days
-
(c) 10 days
-
(d) 8 days
-
(e) 18 days
B
Correct answer
Explanation
Let Bhavya's efficiency be B. Veer's efficiency is 0.6B. Together they complete work in 30 days, so total work is 30 * 1.6B = 48B. Veer takes 48B / 0.6B = 80 days. Bhavya takes 48B / B = 48 days. Abhishek takes 48 - 10 = 38 days. The calculation for all three working together results in 12 days.
-
44
-
45
-
46
-
47
-
None of these
-
a)10 days
-
b)8 days
-
c)12 days
-
d)15 days
-
e)None of these
A
Correct answer
Explanation
P+Q=1/6, Q+R=7/60. P(3) + (Q+R)(6) = 1 => 3P + 6(7/60) = 1 => 3P + 0.7 = 1 => 3P = 0.3 => P = 0.1 (10 days). Q = 1/6 - 1/10 = 1/15. R = 7/60 - 1/15 = 3/60 = 1/20 (20 days). Difference = 20 - 10 = 10 days.
-
a)45 days
-
b)36 days
-
c)30 days
-
d)24 days
-
e)60 days
-
(a) 24 days
-
(b) 25 days
-
(c) 26 days
-
(d) 27 days
-
(e) 28 days
B
Correct answer
Explanation
2M + 3W = 1/20, 3M + 2W = 1/16. Solving these: 6M + 9W = 3/20, 6M + 4W = 2/16. 5W = 3/20 - 1/8 = (6-5)/40 = 1/40. W = 1/200. M = (1/20 - 3/200) / 2 = 7/400. 2M + 1W = 14/400 + 2/400 = 16/400 = 1/25. Time = 25 days.
-
Rs 20
-
Rs 100
-
Rs 180
-
Rs 50
A
Correct answer
Explanation
Ajay's rate is 1/24, Vijay's is 1/30. Together they do 1/24 + 1/30 = 5/120 + 4/120 = 9/120 = 3/40 per day. With Pradeep, they do 1/12 per day. Pradeep's contribution is 1/12 - 3/40 = 10/120 - 9/120 = 1/120 per day. In 12 days, Pradeep does 12 * 1/120 = 1/10 of the work. His share is 1/10 * 200 = 20.
C
Correct answer
Explanation
Work rates: A=1/24, B=1/32, C=1/60. In 6 days, A+B+C do 6*(1/24+1/32+1/60) = 6*(10+7.5+4)/240 = 6*(21.5/240) = 129/240. In next 2 days, B+C do 2*(1/32+1/60) = 2*(15+8)/480 = 46/480 = 23/240. Total work done = 129/240 + 23/240 = 152/240. Remaining work = 88/240. C does this in (88/240) / (1/60) = 88/4 = 22 days.
-
10 days
-
15 days
-
20 days
-
12 days
-
None of these
C
Correct answer
Explanation
The total work is 6 × 10 × 24 = 1440 man-hours. At 9 men working 8 hours daily, the daily work is 72 man-hours, so the required time is 1440/72 = 20 days.
-
48 days
-
44 days
-
46 days
-
40 days
-
None of these
A
Correct answer
Explanation
X's rate = 1/40, Y's rate = 1/60. Together rate = 1/40 + 1/60 = 5/120 = 1/24. Work done in 8 days = 8/24 = 1/3. Remaining work = 2/3. Y completes 2/3 at rate 1/60, time = (2/3) * 60 = 40 days. Total time = 8 + 40 = 48 days.
-
88/17 days
-
144/17days
-
72/17 days
-
8 days
B
Correct answer
Explanation
Sambhu does the whole work in 16 days (1/2 in 8 days). Kalu does the whole work in 18 days (1/3 in 6 days). Their combined rate is 1/16 + 1/18 = (9+8)/144 = 17/144. Time taken is 144/17 days.
-
7 days
-
8 days
-
9 days
-
11 days
C
Correct answer
Explanation
Let Dev work for x days. Dev's daily work is 1/45, Tukku's is 1/40. Tukku worked for (x + 23) days total. The equation is x/45 + (x + 23)/40 = 1. Multiplying by 360 gives 8x + 9(x + 23) = 360, so 17x + 207 = 360, 17x = 153, x = 9.
-
1 day
-
3 day
-
2 days
-
4 days
-
5 days
C
Correct answer
Explanation
A's efficiency = 1/15. B's efficiency = 2/15. Let x be days worked together. A works 11 days, B works x days. (11/15) + (2x/15) = 1. 11 + 2x = 15. 2x = 4. x = 2 days.
-
45 days
-
50 days
-
56 days
-
60 days
-
64 days