Time and Work Questions

Multiple choice
  1. 20 days

  2. 24 days

  3. 18 days

  4. 22 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Vaibhav's work in 15 days = 15/60 = 1/4. Remaining work = 3/4. Sandeep does 3/4 work in 30 days, so Sandeep's rate = (3/4)/30 = 1/40 per day. Combined rate = 1/60 + 1/40 = (2+3)/120 = 5/120 = 1/24. Together they finish in 24 days.

Multiple choice
  1. 32

  2. 36

  3. 40

  4. 45

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let H and R be the daily work of a human and a robot. 15H + 5R = 1/30. 5H + 15R = 1/60. Multiply first by 3: 45H + 15R = 3/30 = 1/10. Subtract second: 40H = 1/10 - 1/60 = 5/60 = 1/12. H = 1/480. 15H = 15/480 = 1/32. Time = 32 days.

Multiple choice
  1. 100

  2. 200

  3. 300

  4. 400

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Amal's rate is 1/10 per day, Bimal's is 1/8 per day, and their combined rate with Kamal is 1/4 per day. Kamal's daily rate is 1/4 - (1/10 + 1/8) = 1/4 - 9/40 = 1/40. Since they work for 4 days, the total work done by Kamal is 4 * (1/40) = 1/10 of the total job, so his share is 1/10 of 1000, which is 100.

Multiple choice
  1. 3 days

  2. 13 days

  3. 10 days

  4. 5 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = 52 men * 10 days = 520 man-days. With 12 men leaving, 40 men remain. Days required = 520 / 40 = 13 days. The increase over the original 10 days is 13 - 10 = 3 days.

Multiple choice
  1. 8

  2. 7

  3. 9

  4. 6

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let C = x, B = 2x, A = 4x. Combined rate = 7x. (7x + 1/16) * 4 = 1. 28x + 1/4 = 1 => 28x = 3/4 => x = 3/112. A's rate = 4x = 12/112 = 3/28. Time for 75% work = (0.75) / (3/28) = (3/4) * (28/3) = 7 days.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≤ Quantity II

  3. Quantity I < Quantity II

  4. Quantity I ≥ Quantity II

  5. Quantity I = Quantity II or No relation

Reveal answer Fill a bubble to check yourself
C Correct answer
Multiple choice
  1. P

  2. Q

  3. R

  4. Any one of the three

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

P, Q, R take x-28, x-18, x-8 days. Their rates are 1/(x-28), 1/(x-18), 1/(x-8). To finish in the least time, the person with the highest rate (shortest time) should start. Since x-28 < x-18 < x-8, P is the fastest.

Multiple choice
  1. 85 days

  2. 80 days

  3. 75 days

  4. 65 days

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let efficiencies be A, B, C. (A+B+C) = 1/20. (A+B) = 1.5C. (A+C) = 2B. Solving the system: A+B+C = 1.5C + C = 2.5C = 1/20 => C = 1/50. A+C = 2B => A+1/50 = 2B. A+B+1/50 = 1/20 => A+B = 3/100. Solving gives A = 1/75. A takes 75 days.