Time and Work Questions

Multiple choice
  1. 52 days

  2. 42 days

  3. 30 days

  4. 50 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let R's work be r. Q = 3r, P = 2Q = 6r. Total work rate = 6r + 3r + r = 10r. They finish in 30 days, so total work = 30 * 10r = 300r. P alone takes 300r / 6r = 50 days.

Multiple choice
  1. 2 days

  2. 3 days

  3. 4 days

  4. 5 days

  5. 6 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Combined rate = 170 + 80 = 250 cookies/hour. Daily capacity = 250 * 12 hours = 3000 cookies/day. Days required = 12000 / 3000 = 4 days.

Multiple choice
  1. 2

  2. 3

  3. 4

  4. 5

  5. 6

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 5 machines * 8 days = 40 machine-days. To finish in 5 days, machines needed = 40 / 5 = 8. Additional machines = 8 - 5 = 3.

Multiple choice
  1. $50
  2. $75
  3. $100
  4. $125
  5. $150
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work rates: M=1/10, N=1/20, O=1/30. M worked 5 days (5/10 = 1/2 work). N worked 5 days (5/20 = 1/4 work). Remaining work = 1 - 1/2 - 1/4 = 1/4. Owen does 1/4 work. Since M got 150 for 1/2 work, 1/4 work is worth 75.

Multiple choice
  1. Quantity A is greater than quantity B.

  2. Quantity B is greater than quantity A.

  3. Both quantities are equal.

  4. The relationship between the quantities cannot be determined.

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Quantity A: 30 * 20 = 600 man-days. People needed for 4 days = 600 / 4 = 150. Quantity B: 50 * 12 = 600 man-days. People needed for 5 days = 600 / 5 = 120. 150 > 120, so Quantity A is greater.

Multiple choice
  1. 10.5

  2. 11

  3. 6

  4. 12.5

  5. 13

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

The total work is 9 men * 7.5 hours * 20 days = 1350 man-hours. Given 2 men (latter) = 3 men (former), 1 latter man = 1.5 former men. So 12 latter men = 18 former men. Work = 18 * 6 * D = 1350. D = 1350 / 108 = 12.5.

Multiple choice
  1. 10 days

  2. 12 days

  3. 15 days

  4. 16 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Balram and Chandan's combined rate = 1/20 + 1/30 = 5/60 = 1/12. In 2 days, they complete 2/12 = 1/6 of the work. Remaining work = 5/6. Abhay's rate = 1/18. Time for Abhay = (5/6) / (1/18) = 15 days.

Multiple choice
  1. 20 days

  2. 30 days

  3. 45 days

  4. 25 days

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Since the ratio of the work capacities of A and B is 3:2, we can assume A does 3 units of work per day and B does 2 units. Together they do 5 units of work per day, so the total work is 5 * 18 = 90 units. A alone will take 90 / 3 = 30 days to complete this work.

Multiple choice
  1. 9 days

  2. 10 days

  3. 11 days

  4. 12 days

  5. 14 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A's daily work = 1/10, B's daily work = 1/15. In a 2-day cycle, they complete 1/10 + 1/15 = 5/30 = 1/6 of the work. In 10 days (5 cycles), they complete 5/6 of the work. On day 11, A does 1/10, total 5/6 + 1/10 = 16/15 (too much). A completes 1/6 of the remaining 1/6 on day 11, and B finishes the rest on day 12.

Multiple choice
  1. 10 days, 30 days.

  2. 15 days, 20 days.

  3. 20 days, 40 days.

  4. 10 days, 50 days.

  5. None of These

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let rates be A+B=1/12, B+C=1/15, C+A=1/20. Summing these gives 2(A+B+C) = 1/12 + 1/15 + 1/20 = 12/60 = 1/5, so A+B+C = 1/10 (10 days). To find A, subtract B+C: A = 1/10 - 1/15 = 1/30 (30 days).