Time and Work Questions

Multiple choice
  1. 2000

  2. 1000

  3. 4000

  4. 1333.33

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Raman's rate = 1/16, Frank's rate = 1/24. Combined rate of Raman and Frank = 1/16 + 1/24 = 5/48. Together with Ricky, they complete the job in 8 days (rate = 1/8). Ricky's rate = 1/8 - 5/48 = 1/48. The work done by each in 8 days: Raman = 8/16 = 1/2, Frank = 8/24 = 1/3, Ricky = 8/48 = 1/6. Raman's share = (1/2) * 4000 = 2000.

Multiple choice
  1. 6.8 days

  2. 7.8 days

  3. 11.8 days

  4. 13.8 days

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Total work = 48 units. Rates: A=6, B=3, C=2. Day 1: A works (6 units). Remaining = 42. Let total time be T. B and C work for T-1 days. B leaves 4 days before end, so B works for T-5 days. C works for T-1 days. 3(T-5) + 2(T-1) = 42. 3T - 15 + 2T - 2 = 42. 5T = 59. T = 11.8.

Multiple choice
  1. 7 1/2 days

  2. 12 1/2 days

  3. 15

  4. 20

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A and B together do (1/20 + 1/30) = 5/60 = 1/12 of the work per day. In 9 days, they complete 9/12 = 3/4 of the work, leaving 1/4 of the work for B. Since B completes 1/30 of the work per day, B takes (1/4) / (1/30) = 30/4 = 7.5 days.

Multiple choice
  1. 60 days

  2. 46 days

  3. 14 days

  4. 28 days

  5. 37 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let X and Y be the work rates. We have 30(X+Y) = 1, so X+Y = 1/30. Also, 16X + 44Y = 1. Substituting X = 1/30 - Y into the second equation gives 16(1/30 - Y) + 44Y = 1, which simplifies to 16/30 + 28Y = 1, or 28Y = 14/30 = 7/15. Thus Y = 7/(15*28) = 1/60. Y takes 60 days.