Time and Work Questions

Multiple choice
  1. 24

  2. 30

  3. 18

  4. 16

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let the number of persons be N and days be 15. The total work is 15N. If there are N+6 persons, the time taken is 12 days, so the work is 12(N+6). Setting 15N = 12N + 72, we get 3N = 72, so N = 24.

Multiple choice
  1. 480

  2. 600

  3. 800

  4. 1200

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let x be the number of workers. Work = x * 12. Also Work = (x+20) * 10. 12x = 10x + 200, 2x = 200, x = 100. Total work = 100 * 12 = 1200 worker-days.

Multiple choice
  1. 21

  2. 22

  3. 23

  4. 24

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let A and B take 'a' and 'b' days to complete the work. 1/a + 1/b = 1/12. Given 0.5a + 0.5b = 25, so a + b = 50. Solving the system: x^2 - 50x + 600 = 0, giving roots 20 and 30. Since A is slower, A=30, B=20. For the second scenario: (1/5) * 30 + (4/5) * 20 = 6 + 16 = 22 days.

Multiple choice
  1. 28

  2. 30

  3. 24

  4. 27

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let efficiencies be 3x and 7x. Total work = (3x + 7x) * 14 = 140x. B works for 8 days, completing 7x * 8 = 56x. Remaining work is 140x - 56x = 84x. A completes this at 3x efficiency, taking 84x / 3x = 28 days.

Multiple choice
  1. $300
  2. $380
  3. $440
  4. $550
  5. $600
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A's work rate = 1/20, B's = 1/30. In 10 days, A does 10/20 = 1/2 of work. B does 10/30 = 1/3 of work. Total work done by both = 1/2 + 1/3 = 5/6. Remaining work = 1/6, done by B. Total work by B = 1/3 + 1/6 = 1/2. Since A and B did equal amounts of work (1/2 each), they should get equal pay. A got 550, so B gets 550.

Multiple choice
  1. 6

  2. 8

  3. 15

  4. 16

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Team A rate = 1/12, Team B rate = 1/36. In 4 days, A does 4/12 = 1/3. In next 2 days, A+B do 2(1/12 + 1/36) = 2(4/36) = 2/9. Total done = 1/3 + 2/9 = 5/9. Remaining = 4/9. B's new rate = 2/36 = 1/18. Time = (4/9) / (1/18) = 8 days.