Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
A
Correct answer
Explanation
Let the number of persons be N and days be 15. The total work is 15N. If there are N+6 persons, the time taken is 12 days, so the work is 12(N+6). Setting 15N = 12N + 72, we get 3N = 72, so N = 24.
D
Correct answer
Explanation
Let x be the number of workers. Work = x * 12. Also Work = (x+20) * 10. 12x = 10x + 200, 2x = 200, x = 100. Total work = 100 * 12 = 1200 worker-days.
B
Correct answer
Explanation
Let A and B take 'a' and 'b' days to complete the work. 1/a + 1/b = 1/12. Given 0.5a + 0.5b = 25, so a + b = 50. Solving the system: x^2 - 50x + 600 = 0, giving roots 20 and 30. Since A is slower, A=30, B=20. For the second scenario: (1/5) * 30 + (4/5) * 20 = 6 + 16 = 22 days.
-
$1100
-
$520
-
$1080
-
$1170
-
$630
B
Correct answer
Explanation
Work rates are 1/6, 1/8, 1/12. Ratio of work done is 4:3:2. Total parts = 9. C's share = (2/9) * 2340 = 520.
A
Correct answer
Explanation
Let efficiencies be 3x and 7x. Total work = (3x + 7x) * 14 = 140x. B works for 8 days, completing 7x * 8 = 56x. Remaining work is 140x - 56x = 84x. A completes this at 3x efficiency, taking 84x / 3x = 28 days.
-
18 days
-
15 days
-
16 days
-
12 days
D
Correct answer
Explanation
A's work rate = 1/20, B's = 1/30. In 10 days, A does 10/20 = 1/2 of work. B does 10/30 = 1/3 of work. Total work done by both = 1/2 + 1/3 = 5/6. Remaining work = 1/6, done by B. Total work by B = 1/3 + 1/6 = 1/2. Since A and B did equal amounts of work (1/2 each), they should get equal pay. A got 550, so B gets 550.
-
25 days
-
22 days
-
32 days
-
34 days
-
None of these
C
Correct answer
Explanation
Efficiency P = 3 * Efficiency Q. Combined efficiency = 4 units. Work = 4 * 24 = 96 units. Time for P = 96 / 3 = 32 days.
B
Correct answer
Explanation
Team A rate = 1/12, Team B rate = 1/36. In 4 days, A does 4/12 = 1/3. In next 2 days, A+B do 2(1/12 + 1/36) = 2(4/36) = 2/9. Total done = 1/3 + 2/9 = 5/9. Remaining = 4/9. B's new rate = 2/36 = 1/18. Time = (4/9) / (1/18) = 8 days.
-
8 women
-
10 women
-
17 women
-
21 women
-
34 women
-
15 days
-
60 days
-
22.5 days
-
28 days
-
25 days
C
Correct answer
Explanation
Let B take x days, then A takes x/3 days. Given x - x/3 = 60, so 2x/3 = 60, x = 90. B takes 90 days and A takes 30 days. Together they take (90 * 30) / (90 + 30) = 2700 / 120 = 22.5 days.
D
Correct answer
Explanation
Combined rate = 1/20 + 1/30 = 3/60 + 2/60 = 5/60 = 1/12. Time = 12 days.
-
20 days
-
40 days
-
50 days
-
60 days
-
70 days
D
Correct answer
Explanation
Work rate of (Raj + Ram) = 1/10. Work rate of Raj = 1/12. Work rate of Ram = 1/10 - 1/12 = (6-5)/60 = 1/60. Ram takes 60 days.
A
Correct answer
Explanation
Let Nitin's rate be 1/24 and the combined rate be 1/6. Nirdosh's rate is 1/6 - 1/24 = 4/24 - 1/24 = 3/24 = 1/8. Thus, Nirdosh takes 8 days.