A can complete a work in 60 days. B is 25% more efficient than A. They work together for 15 days. C alone completes the remaining work in 14 days. B and C together will complete 5th part of the original work in:

  1. 18 days

  2. 15 days

  3. 16 days

  4. 12 days

Reveal answer Fill a bubble to check yourself
D Correct answer

Keep practicing — related questions

  • Directions: A sentence is given in four parts (P, Q, R, and S). One of the parts contains a grammatical err...
  • Directions: In the following sentence some parts have been underlined and labelled A, B, C and D. Identify ...
  • Directions: In the following sentence some parts have been underlined and labelled A, B, C and D. Identify ...
  • Directions: In the following sentence some parts have been underlined and labelled A, B, C and D. Identify ...
  • Directions: In the following sentence some parts have been underlined and labelled A, B, C and D. Identify ...
  • Directions: In the following sentence some parts have been underlined and labelled A, B and C. Identify the...
  • Directions: In the following sentence some parts have been underlined and labelled A, B and C. Identify the...
  • Directions: In the following sentence some parts have been underlined and labelled A, B and C. Identify the...

Practice this chapter

  • Time and Work (2195 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy