Time and Work Questions

Multiple choice
  1. 8

  2. 9

  3. 10

  4. 12

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

X does 1/45 per day, Y does 1/40 per day. Together for n days: n(1/45 + 1/40) = n(8+9)/360 = 17n/360. Y works alone for 23 days: 23/40 = 207/360. 17n/360 + 207/360 = 1. 17n = 360 - 207 = 153. n = 153/17 = 9.

Multiple choice
  1. 400

  2. 420

  3. 480

  4. 500

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work done = 480 * 10 * 10 = 48000 man-hours for 1/4 work. Total work = 192000 man-hours. Remaining work = 144000 man-hours. Required men = 144000 / (20 * 8) = 144000 / 160 = 900. Additional men = 900 - 480 = 420.

Multiple choice
  1. 1 day

  2. 2 days

  3. 3 days

  4. 4 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let W be work per woman and M be work per man. 5(12W + 16M) = 1, so 60W + 80M = 1. 4(13W + 24M) = 1, so 52W + 96M = 1. Solving the system: 60W + 80M = 52W + 96M => 8W = 16M => W = 2M. Substituting: 60(2M) + 80M = 1 => 200M = 1 => M = 1/200, W = 1/100. For 25W + 50M: 25(1/100) + 50(1/200) = 0.25 + 0.25 = 0.5. Time = 1/0.5 = 2 days.

Multiple choice
  1. 180 days

  2. 60 days

  3. 100 days

  4. 90 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Given 1/A + 1/B = 1/36, 1/B + 1/C = 1/60, and 1/A + 1/C = 1/45. Adding these gives 2(1/A + 1/B + 1/C) = 1/36 + 1/60 + 1/45 = 12/180 = 1/15. Thus, 1/A + 1/B + 1/C = 1/30. Subtracting (1/A + 1/C) from this gives 1/B = 1/30 - 1/45 = 1/90, so B takes 90 days.

Multiple choice
  1. Rs. 10,000

  2. Rs. 6,000

  3. Rs. 12,000

  4. Rs. 8,000

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Tina's rate is 1/12 and Meena's rate is 1/15. The ratio of their work capacities is (1/12) : (1/15) = 5 : 4. Meena's share of the 18,000 is (4 / (5+4)) * 18,000 = (4/9) * 18,000 = 8,000.

Multiple choice
  1. 36 days

  2. 45 days

  3. 60 days

  4. 66 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let rate of C = c. Rate of B = 1.5c. Rate of A = 2 * (1.5c) = 3c. Combined rate = 3c + 1.5c + c = 5.5c. Work = Rate * Time = 5.5c * 12 = 66c. Time for C = Work / c = 66c / c = 66 days.

Multiple choice
  1. Efficiency of 13 women = Efficiency of 18 men

  2. Efficiency of 11 women = Efficiency of 16 men

  3. Efficiency of 13 women = Efficiency of 17 men

  4. Efficiency of 11 women = Efficiency of 15 men

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let W be efficiency of a woman, M be efficiency of a man. (17W + 24M) * 5 = (12W + 23M) * 6. 85W + 120M = 72W + 138M. 13W = 18M.

Multiple choice
  1. 7.2

  2. 8

  3. 12

  4. Cannot be determined

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Tamal's rate is 1/4 per day, Tina's is 1/9 per day. Combined rate is 1/4 + 1/9 = 13/36. In 2 days, they complete 2 * (13/36) = 13/18 of the work. Remaining work is 5/18. Trisha completes 5/18 in 2 days, so her rate is (5/18) / 2 = 5/36 per day. Time for Trisha to finish the whole job is 36/5 = 7.2 days.

Multiple choice
  1. 56

  2. 65

  3. 46

  4. None of the above

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work done = 104 * 30 * 8 = 24960 man-hours. This is 2/5 of total work, so total work = 62400 man-hours. Remaining work = 37440 man-hours. Time remaining = 56 - 30 = 26 days. Men needed = 37440 / (26 * 9) = 160. Additional men = 160 - 104 = 56.