Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
A
Correct answer
Explanation
This is an inverse proportion problem. 20 men * 16 days = 10 men * x days. 320 = 10x. x = 32.
A
Correct answer
Explanation
Let B's efficiency be x, then A's efficiency is 2x. Combined efficiency = 3x. Work = 3x * 18 = 54x. A alone takes 54x / 2x = 27 days.
-
5 days
-
1 days
-
2 days
-
6 days
-
None
D
Correct answer
Explanation
A's rate is 1/10 and B's rate is 1/15. Combined rate is 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6. Thus, they complete the job in 6 days.
D
Correct answer
Explanation
Man-days = Number of men * Number of days = 2 * 5 = 10.
C
Correct answer
Explanation
Work = Men * Days. 20 man-days = M * 10 days. M = 20 / 10 = 2 men.
-
7 DAY
-
2 DAY
-
4 DAY
-
1 DAY
-
5 DAY
D
Correct answer
Explanation
If A takes 2 days and B takes 2 days, their combined rate is 1/2 + 1/2 = 1 job per day. Thus, they take 1 day to finish.
A, B, and C are skilled labourers, each capable of completing a certain task individually within distinct time frames of 12, 30, and 60 days, respectively. They embarked on a collaborative project, initially working together. However, B chose to depart the project after contributing his expertise for a period of 6 days before completion of the project, while C chose to depart 8 days before completion of the project, then what is the total precise duration required to complete the task?
-
12 days
-
10 days
-
9 days
-
8 days
B
Correct answer
Explanation
Let total days be T. A works for T days, B for T-6, C for T-8. (T/12) + (T-6)/30 + (T-8)/60 = 1. Multiply by 60: 5T + 2(T-6) + (T-8) = 60. 5T + 2T - 12 + T - 8 = 60. 8T = 80. T = 10.
-
10 days.
-
12 days.
-
11 days.
-
6 days.
-
7 days.
D
Correct answer
Explanation
Total work = 15 * 12 = 180 units. Work done in 4 days = 15 * 4 = 60 units. Remaining work = 120 units. New men = 15 - 3 + 8 = 20 men. Time = 120 / 20 = 6 days.
D
Correct answer
Explanation
16M = 12 days -> 1M = 192 days. 24C = 18 days -> 1C = 432 days. 12M + 8C rate = 12/192 + 8/432 = 1/16 + 1/54 = 35/432. Work done in 8 days = 8 * 35/432 = 35/54. Remaining = 19/54. New rate (12M + 11C) = 12/192 + 11/432 = 1/16 + 11/432 = 38/432 = 19/216. Time = (19/54) / (19/216) = 216/54 = 4 days.
D
Correct answer
Explanation
X does 1/20 of work per day, Y does 1/12. In 4 days, X does 4/20 = 1/5 of work. Remaining work = 4/5. Together, they do (1/20 + 1/12) = (3+5)/60 = 8/60 = 2/15 per day. Time for remaining work = (4/5) / (2/15) = (4/5) * (15/2) = 6 days. Total time = 4 + 6 = 10 days.
-
10 days
-
12 days
-
14 days
-
16 days
-
20 days
B
Correct answer
Explanation
Total work = 15 * 12 = 180 man-days. After 4 days, 15 * 4 = 60 man-days are done. Remaining work = 180 - 60 = 120 man-days. 5 men leave, so 10 men remain. Days to finish = 120 / 10 = 12 days.
-
28 days
-
18 days
-
30 days
-
22 days
-
none
B
Correct answer
Explanation
Total work = 12 * 18 = 216 man-days. After 6 days, 12 * 6 = 72 man-days are done. Remaining work = 216 - 72 = 144 man-days. Remaining men = 12 - 4 = 8. Days required = 144 / 8 = 18 days.
-
2:6:7
-
4: 5: 3
-
4:8:9
-
3:2:8
-
9:7:5
B
Correct answer
Explanation
The work rates are 1/15, 1/12, and 1/5 per day. The boy's rate is 1/5 - (1/15 + 1/12) = 1/5 - 9/60 = 1/5 - 3/20 = 1/20. The ratio of their work is 1/15 : 1/12 : 1/20, which simplifies to 4:5:3.
-
18 days
-
10 days
-
12 days
-
15 days
-
20 days