Time and Work Questions

Multiple choice
  1. 2 days

  2. 6 days

  3. 3 days

  4. 5 days

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let time for B be x. Then A = 2x, C = 2x/3. Combined rate: 1/(2x) + 1/x + 3/(2x) = 1/2. (1+2+3)/(2x) = 1/2. 6/(2x) = 1/2. 3/x = 1/2, so x = 6. B takes 6 days.

Multiple choice
  1. 5 days

  2. 7 days

  3. 8 days

  4. 9 days

  5. 10 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's rate is 1/10 and B's rate is 1/15. Together, they work at (1/10 + 1/15) = 1/6 of the fence per day. In 4 days, they complete 4/6 = 2/3 of the fence, leaving 1/3 to be finished by B. Since B paints 1/15 per day, it takes B (1/3) / (1/15) = 5 days to finish.

Multiple choice
  1. $350 and $250
  2. $375 and $225
  3. $400 and $200
  4. $425 and $175
  5. $450 and $150
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Sarah completes the task in 12 days, so her daily rate is 1/12. In 8 days, Sarah does 8/12 = 2/3 of the work. David does the remaining 1/3 in 6 days, so his daily rate is (1/3) / 6 = 1/18. The payment should be proportional to work done: Sarah does 2/3 and David does 1/3. Thus, Sarah gets 2/3 of 600 = 400 and David gets 1/3 of 600 = 200.

Multiple choice
  1. 4 days

  2. 6 days

  3. 7 days

  4. 8 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A's rate = 1/10, B's rate = 1/30, C's rate = 1/15. Day 1: A+B work = 1/10 + 1/30 = 4/30 = 2/15. Day 2: A+B+C work = 2/15 + 1/15 = 3/15 = 1/5. In 2 days, they complete 2/15 + 3/15 = 5/15 = 1/3 of the work. In 6 days, they complete 3 * (1/3) = 1 full work.

Multiple choice
  1. 12DAYS

  2. 15DAYS

  3. 8DAYS

  4. 17DAYS

  5. 11DAYS

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let M be Michael's rate. David's rate = 2/3 M. Combined rate = 5/3 M. Total time = 4 days 19 hrs 12 min = 115.2 hours. Total work = (5/3 M) * 115.2 = 192 M. Michael alone takes 192/M = 192 hours = 8 days.

Multiple choice
  1. 390

  2. 480

  3. 570

  4. 660

  5. 750

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let initial workers be x. Total work = 15x. Work done = x + (x-15) + (x-30) + ... + (x-15*19). This is an arithmetic progression with 20 terms. Sum = (20/2) * [2x + (20-1)*(-15)] = 10 * [2x - 285] = 20x - 2850. Setting 20x - 2850 = 15x, 5x = 2850, x = 570.

Multiple choice
  1. 24

  2. 30

  3. 36

  4. 40

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let X, Y, Z be their daily work rates. X+Y = 1/15, Y+Z = 1/20. Given X = 3Z. Substituting X: 3Z+Y = 1/15 and Y+Z = 1/20. Subtracting the equations: 2Z = 1/15 - 1/20 = 1/60, so Z = 1/120. Then Y = 1/20 - 1/120 = 5/120 = 1/24. Y takes 24 days.

Multiple choice
  1. 50%

  2. 60%

  3. 70%

  4. 80%

  5. 90%

Reveal answer Fill a bubble to check yourself
B Correct answer
Multiple choice
  1. 30th

  2. 45th

  3. 74th

  4. 97th

Reveal answer Fill a bubble to check yourself
C Correct answer
Multiple choice
  1. 20 days

  2. 9 days

  3. 14 days

  4. 11 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Mohan's rate is 1/25, Rohan's is 1/20. Together they work at (1/25 + 1/20) = 9/100 per day. In 5 days, they complete 5 * 9/100 = 45/100 = 9/20 of the work. Remaining work is 11/20. Rohan finishes this in (11/20) / (1/20) = 11 days.