Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
2 days
-
6 days
-
3 days
-
5 days
-
Cannot be determined
B
Correct answer
Explanation
Let time for B be x. Then A = 2x, C = 2x/3. Combined rate: 1/(2x) + 1/x + 3/(2x) = 1/2. (1+2+3)/(2x) = 1/2. 6/(2x) = 1/2. 3/x = 1/2, so x = 6. B takes 6 days.
-
5 days
-
7 days
-
8 days
-
9 days
-
10 days
A
Correct answer
Explanation
A's rate is 1/10 and B's rate is 1/15. Together, they work at (1/10 + 1/15) = 1/6 of the fence per day. In 4 days, they complete 4/6 = 2/3 of the fence, leaving 1/3 to be finished by B. Since B paints 1/15 per day, it takes B (1/3) / (1/15) = 5 days to finish.
C
Correct answer
Explanation
Let initial workers be W. Total work = 16W. With 4 more workers, time = 12 days. Total work = 12(W+4). 16W = 12W + 48, so 4W = 48, W = 12.
-
$350 and $250
-
$375 and $225
-
$400 and $200
-
$425 and $175
-
$450 and $150
C
Correct answer
Explanation
Sarah completes the task in 12 days, so her daily rate is 1/12. In 8 days, Sarah does 8/12 = 2/3 of the work. David does the remaining 1/3 in 6 days, so his daily rate is (1/3) / 6 = 1/18. The payment should be proportional to work done: Sarah does 2/3 and David does 1/3. Thus, Sarah gets 2/3 of 600 = 400 and David gets 1/3 of 600 = 200.
-
4 days
-
6 days
-
7 days
-
8 days
B
Correct answer
Explanation
A's rate = 1/10, B's rate = 1/30, C's rate = 1/15. Day 1: A+B work = 1/10 + 1/30 = 4/30 = 2/15. Day 2: A+B+C work = 2/15 + 1/15 = 3/15 = 1/5. In 2 days, they complete 2/15 + 3/15 = 5/15 = 1/3 of the work. In 6 days, they complete 3 * (1/3) = 1 full work.
-
12DAYS
-
15DAYS
-
8DAYS
-
17DAYS
-
11DAYS
C
Correct answer
Explanation
Let M be Michael's rate. David's rate = 2/3 M. Combined rate = 5/3 M. Total time = 4 days 19 hrs 12 min = 115.2 hours. Total work = (5/3 M) * 115.2 = 192 M. Michael alone takes 192/M = 192 hours = 8 days.
C
Correct answer
Explanation
Let initial workers be x. Total work = 15x. Work done = x + (x-15) + (x-30) + ... + (x-15*19). This is an arithmetic progression with 20 terms. Sum = (20/2) * [2x + (20-1)*(-15)] = 10 * [2x - 285] = 20x - 2850. Setting 20x - 2850 = 15x, 5x = 2850, x = 570.
-
30 days
-
60 days
-
90 days
-
120 days
-
180 days
C
Correct answer
Explanation
Let Z's rate be z. Y's rate = 2z. X's rate = 3 * 2z = 6z. Total rate = 6z + 2z + z = 9z. Total work = 10 days * 9z = 90z. Time for Z = 90z / z = 90 days.
B
Correct answer
Explanation
3m + 18w = 1/2 work/day. 6m = 1/3 work/day, so 1m = 1/18 work/day. Substitute m: 3(1/18) + 18w = 1/2. 1/6 + 18w = 1/2. 18w = 1/3. w = 1/54. 9w = 9/54 = 1/6 work/day. Time = 6 days.
C
Correct answer
Explanation
Using the formula (M1*D1*H1)/W1 = (M2*D2*H2)/W2, we have (8*10*8)/1 = (M2*20*8)/3. Solving for M2 gives M2 = (8*10*8*3)/(20*8) = 12.
A
Correct answer
Explanation
Let X, Y, Z be their daily work rates. X+Y = 1/15, Y+Z = 1/20. Given X = 3Z. Substituting X: 3Z+Y = 1/15 and Y+Z = 1/20. Subtracting the equations: 2Z = 1/15 - 1/20 = 1/60, so Z = 1/120. Then Y = 1/20 - 1/120 = 5/120 = 1/24. Y takes 24 days.
-
20 days
-
9 days
-
14 days
-
11 days
D
Correct answer
Explanation
Mohan's rate is 1/25, Rohan's is 1/20. Together they work at (1/25 + 1/20) = 9/100 per day. In 5 days, they complete 5 * 9/100 = 45/100 = 9/20 of the work. Remaining work is 11/20. Rohan finishes this in (11/20) / (1/20) = 11 days.
D
Correct answer
Explanation
Let initial employees be x. Work = 200x. New situation: (x-20) * 220 = 200x. 220x - 4400 = 200x, so 20x = 4400, x = 220.