Time and Work Questions

Multiple choice
  1. the quantity in Column A is greater

  2. the quantity in Column B is greater

  3. the two quantities are equal

  4. the relationship cannot be determined from the information given

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Days 1-10: 40 men * 10 days = 400 units. Days 11-20: 35 men * 10 days = 350 units. Days 21-30: 30 men * 10 days = 300 units. Days 31-40: 25 men * 10 days = 250 units. Days 41-50: 20 men * 10 days = 200 units. Total units = 1600. Remaining work = 1600 - 1500 = 100. Days 51+: 15 men. 100/15 = 6.66 days. Total time = 50 + 6.66 = 56.66 days. Since 56.66 > 56, Column A is greater.

Multiple choice
  1. 4

  2. 6

  3. 8

  4. 10

  5. 12

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let d be the days worked at normal hours. Total work is 10 * 40 = 400 man-days. Work done in d days is 10d. Remaining work (400 - 10d) is done in (34 - d) days by 10 men working at 1.25 efficiency. So, 10d + (34 - d) * 10 * 1.25 = 400. Solving gives 10d + 425 - 12.5d = 400, so 2.5d = 25, d = 10.

Multiple choice
  1. 6 6/13 days

  2. 3 3/13 days

  3. 9 2/5 days

  4. 12 12/13 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

3M = 8 days -> 1M = 24 days. 4B = 7 days -> 1B = 28 days. Work rate of 2M + 2B = 2/24 + 2/28 = 1/12 + 1/14 = (7+6)/84 = 13/84. Time for 1 wall = 84/13 days. Time for 2 walls = 168/13 = 12 12/13 days.

Multiple choice
  1. $2000, $1500, $2500
  2. $1800, $2800, $800
  3. $2000, $1400, $1000
  4. $900, $1600, $1400
  5. $1500, $2000, $2500
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's rate is 1/15, B's is 1/20. Together they do (1/15 + 1/20) = 7/60 per day. In 5 days, they do 35/60 = 7/12 of the work. C does the remaining 5/12 in 10 days, so C's rate is (5/12)/10 = 1/24. The ratio of work done is A: 5/15 = 1/3, B: 5/20 = 1/4, C: 5/12. Ratio is 4:3:5. Dividing 6000 in this ratio: A = 2000, B = 1500, C = 2500.