Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
B
Correct answer
Explanation
5 men = 12 boys. 16 men + 24 boys = (16 * 12/5) + 24 boys = 38.4 + 24 = 62.4 boys. 12 boys take 39 days for 1 unit of work. 62.4 boys take (12 * 39) / 62.4 = 7.5 days for 1 unit. For 2 units, it takes 7.5 * 2 = 15 days.
A
Correct answer
Explanation
A's rate is 1/20, B's is 1/15, C's is 1/12. B and C work for 3 days: 3 * (1/15 + 1/12) = 3 * (4+5)/60 = 27/60 = 9/20. Remaining work = 11/20. A takes (11/20) / (1/20) = 11 days.
-
Rs. 6612.50
-
Rs. 66120
-
Rs. 66125
-
Rs. 6000
A
Correct answer
Explanation
Daily wage = 2645 / 10 = 264.5. Wage for 25 days = 264.5 * 25 = 6612.50.
-
Rs. 100
-
Rs. 300
-
Rs. 400
-
Rs. 800
B
Correct answer
Explanation
Akashi's rate = 1/6, Barack's rate = 1/8. Combined rate = 1/6 + 1/8 = 7/24. In 3 days, they do 3 * (7/24) = 7/8 of the work. Charlie does 1 - 7/8 = 1/8 of the work. Charlie's pay = (1/8) * 2400 = 300.
-
3 days
-
10/3 days
-
20 days
-
64/9 days
-
24 days
-
32 days
-
36 days
-
40 days
D
Correct answer
Explanation
Let M be the work of a man and W be the work of a woman per day. 8(4M + 6W) = 10(3M + 7W) => 32M + 48W = 30M + 70W => 2M = 22W => M = 11W. Total work = 8(4(11W) + 6W) = 8(50W) = 400W. Time for 10 women = 400W / 10W = 40 days.
A
Correct answer
Explanation
Work = Men * Days * Hours. Total work = 81 * 24 * 6 = 11664 man-hours. Work done in 6 days = 81 * 6 * 6 = 2916. Remaining work = 11664 - 2916 = 8748. Remaining men = 81 - 27 = 54. Remaining days = 24 - 6 = 18. Hours needed = 8748 / (54 * 18) = 8748 / 972 = 9.
-
10 days
-
6 days
-
18 days
-
Data insufficient
-
None of these
B
Correct answer
Explanation
X's efficiency = 1 unit/day. Y is 50% more efficient, so Y's efficiency = 1.5 units/day. Combined efficiency = 2.5 units/day. Total work = 15 days * 1 unit/day = 15 units. Time taken = 15 / 2.5 = 6 days.
-
24, 40, 60
-
28, 32, 68
-
183/7, 54, 24
-
None of these
A
Correct answer
Explanation
Let work rates be A, B, C. A+B = 1/15, B+C = 1/24. 5A + 13B + 28C = 1. Using A = 1/15 - B and C = 1/24 - B: 5(1/15 - B) + 13B + 28(1/24 - B) = 1. Solving for B gives B = 1/40. Then A = 1/24 and C = 1/60. Days are 24, 40, 60.
-
Rs. 2000
-
Rs. 2500
-
Rs. 2750
-
Rs. 2250
D
Correct answer
Explanation
A is 3 times as efficient as B. A = 3B. Combined efficiency (A+B) = 4B. They finish in 45 days, so total work = 4B * 45 = 180B. Amount for A = (Efficiency of A / Total Efficiency) * Total Amount = (3B / 4B) * 13500 = 0.75 * 13500 = 10125 for 45 days. Amount for 10 days = (10125 / 45) * 10 = 225 * 10 = 2250.
A
Correct answer
Explanation
Let x be the number of men. Work = x * 9. If 6 are absent, (x-6) * 15 = work. So 9x = 15(x-6) => 9x = 15x - 90 => 6x = 90 => x = 15.
-
96 days
-
78 days
-
108 days
-
88 days
-
72 days
A
Correct answer
Explanation
Let R, S, M be rates. R+S = 1/24, S+M = 1/16, M+R = 1/12. Adding them: 2(R+S+M) = 1/24 + 1/16 + 1/12 = (2+3+4)/48 = 9/48 = 3/16. So R+S+M = 3/32. To find S, subtract (M+R): S = 3/32 - 1/12 = (9-8)/96 = 1/96. Suresh takes 96 days.
-
Rs. 2322.37
-
Rs. 2412.21
-
Rs. 2331.45
-
Rs. 2341.14
-
None of these
A
Correct answer
Explanation
Rates: Sonia = 1/18, Raman = 1/54, Parmit = 1/108. In 10 days, Sonia does 10/18 work. Remaining work = 1 - 10/18 = 8/18 = 4/9. Raman and Parmit finish this together. Their combined rate = 1/54 + 1/108 = 3/108 = 1/36. Time taken = (4/9) / (1/36) = 16 days. Total work done by Raman = 16/54 = 8/27. Share = (8/27) * 7838 = 2322.37.
-
121 days
-
36 days
-
26 days
-
33 days
-
-
B
Correct answer
Explanation
2M = 1W = 3B = 1/66 work per day. So 1M = 1/132, 1W = 1/66, 1B = 1/198. 1M + 1W + 1B = (3+6+2)/396 = 11/396 = 1/36. Time = 36 days.