Time and Work Questions

Multiple choice
  1. 11

  2. 14

  3. 12

  4. 9

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's rate is 1/20, B's is 1/15, C's is 1/12. B and C work for 3 days: 3 * (1/15 + 1/12) = 3 * (4+5)/60 = 27/60 = 9/20. Remaining work = 11/20. A takes (11/20) / (1/20) = 11 days.

Multiple choice
  1. Rs. 100

  2. Rs. 300

  3. Rs. 400

  4. Rs. 800

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Akashi's rate = 1/6, Barack's rate = 1/8. Combined rate = 1/6 + 1/8 = 7/24. In 3 days, they do 3 * (7/24) = 7/8 of the work. Charlie does 1 - 7/8 = 1/8 of the work. Charlie's pay = (1/8) * 2400 = 300.

Multiple choice
  1. 9

  2. 16

  3. 32

  4. 48

  5. 4

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work = Men * Days * Hours. Total work = 81 * 24 * 6 = 11664 man-hours. Work done in 6 days = 81 * 6 * 6 = 2916. Remaining work = 11664 - 2916 = 8748. Remaining men = 81 - 27 = 54. Remaining days = 24 - 6 = 18. Hours needed = 8748 / (54 * 18) = 8748 / 972 = 9.

Multiple choice
  1. 24, 40, 60

  2. 28, 32, 68

  3. 183/7, 54, 24

  4. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let work rates be A, B, C. A+B = 1/15, B+C = 1/24. 5A + 13B + 28C = 1. Using A = 1/15 - B and C = 1/24 - B: 5(1/15 - B) + 13B + 28(1/24 - B) = 1. Solving for B gives B = 1/40. Then A = 1/24 and C = 1/60. Days are 24, 40, 60.

Multiple choice
  1. Rs. 2000

  2. Rs. 2500

  3. Rs. 2750

  4. Rs. 2250

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A is 3 times as efficient as B. A = 3B. Combined efficiency (A+B) = 4B. They finish in 45 days, so total work = 4B * 45 = 180B. Amount for A = (Efficiency of A / Total Efficiency) * Total Amount = (3B / 4B) * 13500 = 0.75 * 13500 = 10125 for 45 days. Amount for 10 days = (10125 / 45) * 10 = 225 * 10 = 2250.

Multiple choice
  1. 96 days

  2. 78 days

  3. 108 days

  4. 88 days

  5. 72 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let R, S, M be rates. R+S = 1/24, S+M = 1/16, M+R = 1/12. Adding them: 2(R+S+M) = 1/24 + 1/16 + 1/12 = (2+3+4)/48 = 9/48 = 3/16. So R+S+M = 3/32. To find S, subtract (M+R): S = 3/32 - 1/12 = (9-8)/96 = 1/96. Suresh takes 96 days.

Multiple choice
  1. Rs. 2322.37

  2. Rs. 2412.21

  3. Rs. 2331.45

  4. Rs. 2341.14

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Rates: Sonia = 1/18, Raman = 1/54, Parmit = 1/108. In 10 days, Sonia does 10/18 work. Remaining work = 1 - 10/18 = 8/18 = 4/9. Raman and Parmit finish this together. Their combined rate = 1/54 + 1/108 = 3/108 = 1/36. Time taken = (4/9) / (1/36) = 16 days. Total work done by Raman = 16/54 = 8/27. Share = (8/27) * 7838 = 2322.37.