Time and Work Questions

Multiple choice
  1. ₹13,200

  2. ₹16,500

  3. ₹14,400

  4. None of the above

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A's efficiency be a. 1.2a * (T-3) = a * T -> 1.2T - 3.6 = T -> 0.2T = 3.6 -> T = 18 days. A's rate = 1/18. A+B together at 11.11% (1/9) more efficiency: (1+1/9) * (A+B) * (T-1) = 1. (10/9) * (A+B) * 17 = 1. (A+B) = 9/170. B = 9/170 - 1/18 = (81-85)/1530 = -4/1530. This implies the problem constraints are inconsistent.

Multiple choice
  1. 80%

  2. 83.33%

  3. 87.5%

  4. 78%

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let W, B, M be daily work of woman, boy, man. 5B + M = 0.5(3W + 4B + 2M) => 10B + 2M = 3W + 4B + 2M => 3W = 6B => W = 2B. 2W + 2M = (2/3)(3W + 4B + 2M) => 6W + 6M = 6W + 8B + 4M => 2M = 8B => M = 4B. Target: 2W + 3B + 2M = 2(2B) + 3B + 2(4B) = 4B + 3B + 8B = 15B. Total work = 3W + 4B + 2M = 3(2B) + 4B + 2(4B) = 6B + 4B + 8B = 18B. Percentage = 15/18 = 5/6 = 83.33%.

Multiple choice
  1. 2.5%

  2. 3.25%

  3. 2.75%

  4. 3.75%

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 240 * 10 = 2400 man-days. Work done: Day 1 = 240, Day 2 = 238, ..., Day 10 = 222. This is an arithmetic progression with 10 terms. Sum = (10/2) * (240 + 222) = 5 * 462 = 2310. Work left = 2400 - 2310 = 90. Percent left = (90 / 2400) * 100 = 3.75%.

Multiple choice
  1. 12 days

  2. 12.75 days

  3. 11.25 days

  4. 11 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A and V be the efficiencies. (A+V)*8*10 = Work. (0.75A + 1.25V)*8*9 = Work. Solving these gives A = V. Then (1.25A + 0.75A)*8*T = Work. T = 80/1.6 = 11.25 days.

Multiple choice
  1. 5

  2. 6

  3. 7

  4. 8

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let M be the time for Mina. G+S+M = 1/4. G+S = 1/(M-15). So 1/(M-15) + 1/M = 1/4. Solving M^2 - 23M + 60 = 0 gives M=20 or M=3. Since M>15, M=20. G+S = 1/5. Mina works 4 days (2+2), G+S work 2 days. Work done = 4/20 + 2/5 = 1/5 + 2/5 = 3/5. Remaining 2/5 work done by G+S in (2/5) / (1/5) = 2 days. Total time = 4 + 2 = 6 days.

Multiple choice
  1. 2

  2. 4

  3. 3

  4. Cannot be determined

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let the efficiencies be 1/x, 1/y, 1/z in harmonic progression. The problem provides insufficient constraints to uniquely determine the individual efficiencies or the time taken by A alone, as the harmonic progression condition and the work-rate equation do not yield a unique solution for the variables.

Multiple choice
  1. 25

  2. 20

  3. 30

  4. 15

Reveal answer Fill a bubble to check yourself
A Correct answer
Multiple choice
  1. 3 20

  2. 3 10

  3. 1 5

  4. 1 20

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Sam rate = 1/20. Mohit rate = 2/20 = 1/10. Ayna rate = (1/10)/3 = 1/30. In 3 days: (S+M) + (S+A) + (M+A) = 2(S+M+A) = 2(1/20 + 1/10 + 1/30) = 2(6/60 + 3/60 + 2/60) = 2(11/60) = 11/30. Sam works on day 1 and 2, total 2/20 = 1/10. The pattern repeats. Total work = 1. The fraction is 3/10.

Multiple choice
  1. Only (i) and (iii)

  2. Only (ii) and (iv)

  3. Only (ii) and (v)

  4. Only (i), (iii) and (v)

  5. All of the above

Reveal answer Fill a bubble to check yourself
D Correct answer
Multiple choice
  1. 8

  2. 10

  3. 12

  4. 6

  5. 4

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Rates are D=1/30, E=1/24, F=1/20. Work done by D and F in y days is y(1/30 + 1/20) = y(5/60) = y/12. Remaining work is 1 - y/12. E completes this in 4y days: 4y(1/24) = 1 - y/12. So y/6 = 1 - y/12, which means 3y/12 = 1, so y = 4. Thus 2y = 8.

Multiple choice
  1. 15

  2. 19

  3. 21

  4. 23

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A and B be the rates of Aditi and Bhavna. Total time from 8 AM to 8 PM is 12 hours. Aditi works 12 hours, Bhavna works 9 hours. 12A + 9B = 1 (project). If they started together, they finish in 10.5 hours: 10.5(A+B) = 1. Solving the system: 12A + 9B = 1 and 10.5A + 10.5B = 1. From second, B = 1/10.5 - A. Substitute into first: 12A + 9(1/10.5 - A) = 1 => 3A = 1 - 9/10.5 = 1.5/10.5 = 1/7. A = 1/21. Aditi takes 21 hours.

Multiple choice
  1. 12th day

  2. 13th day

  3. 14th day

  4. 15th day

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Ayesha rate = 1/30, Rohan = 1/24, Kabir = 1/40. Day 1: A+R = 1/30 + 1/24 = 9/120 = 3/40. Day 2: R+K = 1/24 + 1/40 = 8/120 = 1/15. Cycle of 2 days = 3/40 + 1/15 = 17/120. In 14 days (7 cycles), work done = 7 * 17/120 = 119/120. Remaining 1/120 on Day 15 by A+R, which is enough.