Time and Work Questions

Multiple choice
  1. 19/3 days

  2. 57/11 days

  3. 53/12 days

  4. 6.5 days

  5. none of the above

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

X, Y, and Z have rates of 1/10, 1/15, and 1/18 of the job per day. Y and Z work for 3 days, completing 3 * (1/15 + 1/18) = 3 * (6/90 + 5/90) = 3 * (11/90) = 11/30 of the job. X must finish the remaining 19/30 of the job at a rate of 1/10 per day, taking (19/30) / (1/10) = 19/3 days.

Multiple choice
  1. 7 days

  2. 10(⅓) days

  3. 11(⅔) days

  4. 10 days

  5. None

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Since A is 40% more efficient than B, their efficiency ratio is 140:100, or 7:5. If A completes the work in 20 days, the total work can be represented as 7 * 20 = 140 units. Working together, their combined efficiency is 7 + 5 = 12 units per day, so they will complete the work in 140 / 12 = 11 2/3 days.

Multiple choice
  1. ₹1675

  2. ₹1079

  3. ₹1200

  4. ₹1145

  5. ₹1935

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/12, B's rate = 1/18. A and B work for 4 days: 4 * (1/12 + 1/18) = 4 * (5/36) = 5/9. Remaining work = 4/9. B and C do this in 5 days: 5 * (1/18 + C_rate) = 4/9. 1/18 + C_rate = 4/45. C_rate = 4/45 - 1/18 = (8-5)/90 = 3/90 = 1/30. Total work done by C = 5 * (1/30) = 5/30 = 1/6. C's share = (1/6) * 7200 = 1200.

Multiple choice
  1. I alone sufficient

  2. II alone sufficient

  3. Either I or II sufficient

  4. Both not sufficient

  5. Both necessary

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

We know C's rate is 1/15. Statement I gives A+B's rate as 1/5.625 = 16/90 = 8/45. Together A+B+C = 8/45 + 3/45 = 11/45. This is sufficient. Statement II gives B+C's rate as 1/9. We don't know A's rate. Thus, I alone is sufficient.

Multiple choice
  1. 8 days

  2. 9 days

  3. 7.5 days

  4. 6 days

  5. 8.4 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work be 36 units. A does 3 units/day, B does 2 units/day. Let total days be x. B works for x days, A works for x-3 days. 3(x-3) + 2x = 36. 3x - 9 + 2x = 36. 5x = 45. x = 9 days.

Multiple choice
  1. 16 days

  2. 18 days

  3. 20 days

  4. 22 days

  5. 15 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Use the formula (M1 * D1 * H1) / W1 = (M2 * D2 * H2) / W2. (16 * 18 * 8) / 2400 = (24 * D2 * 9) / 3600. 2304 / 2400 = 216 * D2 / 3600. 0.96 = 0.06 * D2. D2 = 0.96 / 0.06 = 16 days.

Multiple choice
  1. 150rs

  2. 180rs

  3. 200rs

  4. 220rs

  5. 240rs

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Man's rate = 1/20. Together rate = 1/12. Boy's rate = 1/12 - 1/20 = (5-3)/60 = 2/60 = 1/30. Ratio of work = 1/20 : 1/30 = 3:2. Boy's share = (2/5)*500 = 200.

Multiple choice
  1. 18

  2. 24

  3. 9

  4. 12

  5. NA

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done = 25% in 8 days with 18 workers. Remaining work = 75% in 16 days (24-8). Let X be total workers needed. (18 * 8) / 0.25 = (X * 16) / 0.75. 144 / 0.25 = 16X / 0.75. 576 = 21.33X. Or simply: 18 workers do 25% in 8 days. To do 75% in 16 days, we need (18 * 3) / 2 = 27 workers. Additional workers = 27 - 18 = 9.

Multiple choice
  1. Only A is sufficient.

  2. Only B and C together are sufficient.

  3. Only C is sufficient.

  4. Either A alone or B and C together are sufficient.

  5. None of A, B and C is sufficient.

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Statement A provides the efficiency ratio between Rohit and Rohan, allowing us to find Rohit's time. Statements B and C together allow us to find Pankaj's efficiency relative to Rohan and then Rohit's time. Thus, either A alone or B and C together are sufficient.