Time and Work Questions

Multiple choice
  1. 17 days

  2. 18 days

  3. 16 days

  4. 15 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work rates: A=1/10, B=1/20, C=1/30. Cycle (C, B, A): 1/30 + 1/20 + 1/10 = (2+3+6)/60 = 11/60. In 15 days (5 cycles), work done = 5 * 11/60 = 55/60. Remaining = 5/60 = 1/12. Day 16 (C): 1/30 done. Day 17 (B): 1/20 done. Total work is completed on day 17.

Multiple choice
  1. 34,400

  2. 38,400

  3. 47,040

  4. 38,880

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

To minimize cost, use the most efficient workers. Arun (1/24), Varun (1/21), Tarun (1/15). Tarun is fastest. To finish in 10 days, we need total work = 1. Tarun does 10/15 = 2/3. Remaining 1/3 work can be done by Varun in (1/3)*21 = 7 days. Total cost = 10*2160 + 7*2400 = 21600 + 16800 = 38400.

Multiple choice
  1. 30

  2. 45

  3. 60

  4. 75

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A and M be rates. (A+M)*36 = 1. (0.6A + 1.6M)*36 = 1. So A+M = 0.6A + 1.6M => 0.4A = 0.6M => A = 1.5M. Substitute into A+M = 1/36: 2.5M = 1/36 => M = 1/(36*2.5) = 1/90. A = 1.5/90 = 1/60. The quicker one is A, taking 60 days.

Multiple choice
  1. 17

  2. 18

  3. 19

  4. 20

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let S, A, P be the work rates. (S+A+P) >= 1/10. (S+P) < 1/25. 8(S+A+P) + 4A = 1. If Arjun takes T days, A = 1/T. 8(S+P+1/T) + 4/T = 1 => 8(S+P) + 12/T = 1. Since S+P < 1/25, 8(S+P) < 8/25 = 0.32. So 1 - 12/T < 0.32 => 12/T > 0.68 => T < 17.64. Also (S+A+P) >= 1/10 => 1/T + (S+P) >= 1/10. Since S+P < 1/25, 1/T > 1/10 - 1/25 = 3/50 = 0.06 => T < 16.66. The value 17 is not possible.

Multiple choice
  1. 11,100

  2. 11,400

  3. 14,100

  4. 14,400

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work rates: A=1/12, B=1/18, C=1/36. Combined rate = (3+2+1)/36 = 6/36 = 1/6. Job takes 6 days. Total wages = 6 * (900 + 600 + 400) = 6 * 1900 = 11400.

Multiple choice
  1. 8

  2. 9

  3. 10

  4. 12

  5. 15

Reveal answer Fill a bubble to check yourself
C Correct answer
Multiple choice
  1. 18 days

  2. 24 days

  3. 20 days

  4. 21 days

  5. None

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/15, B's rate = 1/25. Combined = 8/75. In 5 days, they do 40/75 = 8/15. Remaining = 7/15. A and C do this in 4 days, so (1/15 + C) * 4 = 7/15 => 1/15 + C = 7/60 => C = 3/60 = 1/20. C takes 20 days.

Multiple choice
  1. 4(1/2)

  2. 4(2/3)

  3. 5(1/11)

  4. 5(1/9)

  5. 7(1/9)

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let the total work be 24 units. The daily work rates for Jassi, Pammi, and Mani are 3, 2, and 6 units respectively. In a 3-day cycle, Jassi works alone for 2 days (6 units) and all three work together on the third day (11 units), totaling 17 units. On days 4 and 5, Jassi adds 6 units, leaving 1 unit which is completed by all three together in 1/11 of day 6, totaling 5(1/11) days.