Veer can complete a renovation project in 2x + 5 days, while Simran can do it in x days and Kabir in 2x days. Veer works alone for 3 days, after which Simran, Kabir, and Diya join him, and together they complete the remaining work in 4 more days. If the total payment for the project is Rs. 32,000 and Diya's share is 12% of the total payment, then in how many days can Simran complete the renovation work alone?