Calculate notional profit on a contract undertaken of which 80% work has been completed.
Total expenditure to date - Rs. 95,000
Estimated further expenditure to complete the contract (including contingencies) - Rs. 34,000
Contract price - Rs. 1,83,000
Work certified - Rs. 2,02,000
Work not certified - Rs. 8,500
Cash received - Rs. 81,600