Cost Accounts - 1

Practice questions on Cost Concepts, Inventory Control Techniques, Process Costing etc

25 Questions Published

Questions

Question 1 Multiple Choice (Single Answer)

The cost reported by conventional financial accounts is based on

  1. escapable costs
  2. historical costs
  3. replacement costs
  4. joint costs
Question 2 Multiple Choice (Single Answer)

The cost known as diiferential cost is

  1. incremental cost
  2. abandonment cost
  3. opportunity cost
  4. committed cost
Question 3 Multiple Choice (Single Answer)

Which of the following is not included in direct material costs?

  1. Indirect Taxes
  2. Quantity Discounts
  3. Packing and Container Charges
  4. Direct Taxes
Question 4 Multiple Choice (Single Answer)

The annual demand for an item is 6,400 units. What is the time period between two consecutive orders in a year when the economic order quantity is 800 units?

  1. 3 orders per year
  2. 8 orders per year
  3. 2 orders per year
  4. 7 orders per year
Question 5 Multiple Choice (Single Answer)

The annual demand for an item is 6,400 units. What is the time period between two consecutive orders in a year, when the economic order quantity is 800 units?

  1. 3 months
  2. 1.5 months
  3. 2 months
  4. None of the above
Question 6 Multiple Choice (Single Answer)

Ship building is an example of

  1. Contract Costing
  2. Process Costing
  3. Output Costing
  4. None of these
Question 7 Multiple Choice (Single Answer)

A company purchases 250 litres of oil for Rs. 12,600 from the market. Due to leakage, the oil is reduced to 240 litres in weight. At what price must the oil be charged per litre to cover the loss due to leakage, and by how much is the price inflated per litre?

  1. Price to be charged - Rs. 51 per litre. Price inflated by Rs. 2 per litre
  2. Price to be charged - Rs. 52 per litre. Price inflated by Rs. 3 per litre
  3. Price to be charged - Rs. 52.50 per litre. Price inflated by Rs. 2.10 per litre
  4. None of the above
Question 8 Multiple Choice (Single Answer)

When a company pays its workers on the basis of number of pieces of a product produced, it uses

  1. job cards
  2. clock cards
  3. piece work cards
  4. weekly time sheets
Question 9 Multiple Choice (Single Answer)

If the minimum stock level and average stock of raw material A are 5,000 and 8,000 units respectively, find the reorder quantity.

  1. 5,000 units
  2. 6,000 units
  3. 6,500 units
  4. 5,500 units
Question 10 Multiple Choice (Single Answer)

Calculate the order point when it takes 3 months to receive delivery from the date of order and the usage is fairly constant at 6,000 units per month and a safety stock of 3000 units is desired.

  1. 21,000 units
  2. 18,000 units
  3. 20,000 units
  4. 22,000 units
Question 11 Multiple Choice (Single Answer)

Calculate profit to be transferred to Profit and Loss A/c when 75% of work is certified, notional profit is 1,50,000 and cash received is 80% of work certified.

  1. Rs. 80,000
  2. Rs. 1,00,000
  3. Rs. 1,10,000
  4. Rs. 90,000
Question 12 Multiple Choice (Single Answer)

Calculate notional profit on a contract undertaken of which 80% work has been completed.

Total expenditure to date - Rs. 95,000
Estimated further expenditure to complete the contract (including contingencies) - Rs. 34,000
Contract price - Rs. 1,83,000
Work certified - Rs. 2,02,000
Work not certified - Rs. 8,500
Cash received - Rs. 81,600

  1. Rs. 1,10,500
  2. Rs. 1,15,500
  3. Rs. 1,12,500
  4. Rs. 1,15,200
Question 13 Multiple Choice (Single Answer)

Calculate average stock level if minimum stock level is 1,460 units and re-order quantity is 2,000 units.

  1. 2,460 units
  2. 2,000 units
  3. 2,500 units
  4. 2,350 units
Question 14 Multiple Choice (Single Answer)

From the following data, find out the Labour Turnover by applying Replacement Method.

Number of workers on the payroll:
At the beginning of the month - 600
At the end of the month - 800
During the month, 5 workers left, 20 persons were discharged and 80 workers were recruited. Of these, 10 workers were recruited in the vacancies of those who had left while the rest were engaged for an expansion scheme.

  1. 10%
  2. 2%
  3. 2.5%
  4. 1.42%
Question 15 Multiple Choice (Single Answer)

Calculate total estimated profit on a contract undertaken of which 80% work has been completed.

Total expenditure to date - Rs. 95,000
Estimated further expenditure to complete the contract ( including contingencies ) - Rs. 34,000
Contract price - Rs. 1,83,000
Work certified - Rs. 2,02,000
Work not certified - Rs. 8,500
Cash received - Rs. 81,600

  1. Rs. 52,000
  2. Rs. 53,000
  3. Rs. 54,000
  4. Rs. 51,000
Question 16 Multiple Choice (Single Answer)

A worker C is allowed time of 50 hours for completion of the job and the hourly rate is Rs. 10. The actual time taken by the worker is 40 hours. Calculate wages under Rowan Plan.

  1. Rs. 480
  2. Rs. 450
  3. Rs. 475
  4. Rs. 460
Question 17 Multiple Choice (Single Answer)

From the following data, find out the Labour Turnover by Separation Method.

Number of workers on the payroll:
At the beginning of the month - 600
At the end of the month - 800
During the month, 5 workers left, 20 persons were discharged and 80 workers were recruited. Of these, 10 workers were recruited in the vacancies of those who had left while the rest were engaged for an expansion scheme.

  1. 3%
  2. 3.2%
  3. 3.57%
  4. 3.7%
Question 18 Multiple Choice (Single Answer)

From the following data, find out the Labour Turnover by applying Flux Method.

Number of workers on the payroll:
At the beginning of the month - 600
At the end of the month - 800
During the month, 5 workers left, 20 persons were discharged and 80 workers were recruited. Of these, 10 workers were recruited in the vacancies of those who had left while the rest were engaged for an expansion scheme.

  1. 18%
  2. 15%
  3. 12%
  4. 12.5%
Question 19 Multiple Choice (Single Answer)

A worker C is allowed time of 50 hours for completion of the job and the hourly rate is Rs. 10. The actual time taken by the worker is 40 hours. Calculate wages under Halsey Plan.

  1. Rs. 425
  2. Rs. 430
  3. Rs. 450
  4. Rs. 445
Question 20 Multiple Choice (Single Answer)

The labour turnover rates for the year ended 31st March, 2010 are 10%, 5% and 3% respectively under' Flux method', 'Replacement method 'and ' Separation method'. If the number of workers replaced during the given period is 60, calculate the number of workers left and discharged.

  1. 35
  2. 36
  3. 34
  4. 42
Question 21 Multiple Choice (Single Answer)

The residue material that has a recovery value is known as

  1. waste
  2. spoilage
  3. scrap
  4. defective
Question 22 Multiple Choice (Single Answer)

The labour turnover rates for the year ended 31st March, 2010 are 10%, 5% and 3% respectively under' Flux method', 'Replacement method 'and ' Separation method'. If the number of workers replaced during the given period is 60, find out the average number of workers.

  1. 1,000
  2. 1,100
  3. 1,200
  4. 1,150
Question 23 Multiple Choice (Single Answer)

The labour turnover rates for the year ended 31st March, 2010 are 10%, 5% and 3% respectively under' Flux method', 'Replacement method 'and' Separation method'. If the number of workers replaced during the given period is 60, calculate the number of workers recruited and joined during the period.

  1. 80
  2. 82
  3. 90
  4. 84
Question 24 Multiple Choice (Single Answer)

Three batches of materials A, B and C cost Rs.10, Rs. 15, and Rs. 17 respectively. Calculate the cost of material by simple average cost method.

  1. Rs. 15
  2. Rs. 14
  3. Rs. 14.50
  4. Rs.16
Question 25 Multiple Choice (Single Answer)

The total mixed cost of an organization having production of 8,000 units is Rs. 3,60,000. Calculate the variable cost per unit if fixed cost is Rs. 2,00,000.

  1. Rs. 18
  2. Rs. 22
  3. Rs. 19
  4. Rs. 20