Sonia, Arjun, and Priya, working together, would have taken at least 10 days to complete a project. Sonia and Priya, working together, would have taken less than 25 days to complete the same project. In reality, all three worked together for 8 days, followed by Arjun, who worked alone for 4 more days to finish the project. If Arjun had worked alone on the project, then the number of days he would have taken to complete it cannot be
Reveal answer
Fill a bubble to check yourself