A contractor agrees to complete a work in 24 days. He employs 18 workers initially. After 8 days, he realizes that only 25% of the work has been completed. How many additional workers are required to complete the remaining work on time, assuming all workers work at the same rate?
Reveal answer
Fill a bubble to check yourself