Multiple choice

A can complete a job in twice the time that C and D take to complete the job, working together, and in 25% more time than that B and C take to complete the job, working together. If B is half as efficient as D and can complete the job in 40 days, working alone, then, in how many days can all three of them, working together, complete the job?

  1. 6

  2. 4

  3. 9

  4. 8

Reveal answer Fill a bubble to check yourself
D Correct answer
AI explanation

Let the work be 80 units, so D's efficiency is 2 units/day and B's efficiency is 1 unit/day. A takes 25% more time than B and C together, so A's efficiency is 4/5 of the combined efficiency of B and C, giving 4/5 x (1 + c) = a. Since A takes twice the time of C and D together, A's efficiency is half of their combined efficiency, giving 1/2 x (c + 2) = a. Equating the two expressions for A gives 4/5 x (1 + c) = 1/2 x (c + 2), which solves to c = 2 units/day. Substituting C's efficiency gives a = 2 units/day. The combined efficiency of A, B, and C is 2 + 1 + 2 = 5 units/day, so they complete the 80 units of work in 80 divided by 5, which is 8 days. The result is 8.