Ayesha, Rohan, and Kabir are assigned a painting project. Ayesha can complete the project alone in 30 days, Rohan in 24 days, and Kabir in 40 days. Rohan works on the project daily. Ayesha works only on alternate days beginning from Day 1, while Kabir assists only on alternate days starting from Day 2. On which day will the project be completed?