Multiple choice

12 men can complete a work in 18 days. After working for 6 days, 4 men leave the job. How many more days will the remaining men take to finish the work?

  1. 28 days

  2. 18 days

  3. 30 days

  4. 22 days

  5. none

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 12 * 18 = 216 man-days. After 6 days, 12 * 6 = 72 man-days are done. Remaining work = 216 - 72 = 144 man-days. Remaining men = 12 - 4 = 8. Days required = 144 / 8 = 18 days.

AI explanation

The total work is 12 men multiplied by 18 days, which equals 216 man-days. The work done in the first 6 days is 12 men multiplied by 6 days, equaling 72 man-days, leaving 144 man-days of work. The remaining 8 men will take 144 man-days divided by 8 men, which equals 18 days.