A contractor has two teams of workers, team A and team B. Team A can complete a project P in 12 days and team B can complete it in 36 days. Team A starts working on P and team B joins team A after four days. Team A is withdrawn after another two days and team B is asked to double its efficiency. The number of additional days required for team B to complete P is