It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?

  1. 3 days

  2. 13 days

  3. 10 days

  4. 5 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = 52 men * 10 days = 520 man-days. With 12 men leaving, 40 men remain. Days required = 520 / 40 = 13 days. The increase over the original 10 days is 13 - 10 = 3 days.