Time and Work Questions

Multiple choice
  1. $3$ days
  2. $4$ days
  3. $5$ days 
  4. $6$ days
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Thomas paints 1/6 of the house per day, and Joe paints 1/12 of the house per day. Together, their combined rate is 1/6 + 1/12 = 3/12 = 1/4 of the house per day. Therefore, it takes them 4 days to complete the entire house.

Multiple choice
  1. $1260$
  2. $700$
  3. $900$
  4. $870$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work shares are proportional to efficiency (1/time). Efficiencies: Raman = 1/5, Jatin = 1/7, Sachin = 1/9. Ratio = 63:45:35. Total parts = 143. Raman's share = (63/143) * 2860 = 63 * 20 = 1260.

Multiple choice
  1. Data in statement I alone is sufficient.

  2. Data in statement II alone is sufficient.

  3. Data in both statements together is sufficient.

  4. Either of the Statements I and II is sufficient

  5. Data in both statements together is not sufficient.

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let T = mn/(m+n) be the time taken together. (1) 2T > m implies 2n/(m+n) > 1, so 2n > m+n, n > m. (2) 2T < n implies 2m/(m+n) < 1, so 2m < m+n, m < n. Both statements independently prove m < n.

Multiple choice
  1. $12.5\%$
  2. $14.3\%$
  3. $16.7\%$
  4. $25\%$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Rishi's rate is 28/4 = 7 widgets/hr. Shane's rate is 27/5 = 5.4 widgets/hr. To finish the same number of widgets (let this be W) at the same time, they must work for the same duration. If they work for time T, 7T + 5.4T = 2W. Solving for T in terms of W, then finding how much of Shane's work Rishi covers, leads to the percentage.

Multiple choice
  1. Time taken by $1$ woman alone to finish the work: $24$ days, and also that taken by $1$ man alone: $32$ days
  2. Time taken by $1$ woman alone to finish the work: $18$ days, and also that taken by $1$ man alone: $36$ days
  3. Time taken by $1$ woman alone to finish the work: $14$ days, and also that taken by $1$ man alone: $30$ days
  4. Time taken by $1$ woman alone to finish the work: $12$ days, and also that taken by $1$ man alone: $28$ days
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let W be the work of a woman and M be the work of a man per day. 2W + 5M = 1/4 and 3W + 6M = 1/3. Solving this system of linear equations yields W = 1/18 and M = 1/36. Thus, a woman takes 18 days and a man takes 36 days.

Multiple choice
  1. One boy alone can do a piece of work in $130$ days

    and one man alone can do a piece of work in $160$ days
  2. One boy alone can do a piece of work in $90$ days

    and one man alone can do a piece of work in $70$ days
  3. One boy alone can do a piece of work in $120$ days

    and one man alone can do a piece of work in $20$ days
  4. One boy alone can do a piece of work in $160$ days

    and one man alone can do a piece of work in $12$ days
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let M and B be the daily work of a man and a boy. 8(2M + 3B) = 1 => 16M + 24B = 1. 6(3M + 2B) = 1 => 18M + 12B = 1. Solving the system: multiply second by 2: 36M + 24B = 2. Subtracting first: 20M = 1 => M = 1/20. Then 12B = 1 - 18(1/20) = 1 - 0.9 = 0.1 => B = 1/120. Man takes 20 days, boy takes 120 days.

Multiple choice
  1. 6

  2. 10

  3. 8

  4. 7.5

  5. 3.5

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

John's rate is 1/20, Jane's is 1/12. Let T be total time. John works for T days, Jane for T-4 days. (T/20) + (T-4)/12 = 1. Multiply by 60: 3T + 5(T-4) = 60. 3T + 5T - 20 = 60, 8T = 80, T = 10.

Multiple choice
  1. Quantity A is greater.

  2. Quantity B is greater.

  3. The two quantities are equal.

  4. The relationship cannot be determined from the information given.

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Their work rates are proportional to 1/20, 1/30, and 1/40, or 6:4:3. Their earnings follow this ratio, so the difference between A's and B's earnings is twice the difference between B's and C's earnings.

Multiple choice
  1. Quantity A is greater than quantity B.

  2. Quantity B is greater than quantity A.

  3. Both quantities are equal.

  4. The relationship between the quantities cannot be determined.

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

B's efficiency = 1 unit/day. A's efficiency = 0.5 units/day. Together = 1.5 units/day. Days to complete = 12/1.5 = 8 days. Quantity A (8) > Quantity B (7).

Multiple choice
  1. Quantity A is greater.

  2. Quantity B is greater.

  3. The two quantities are equal.

  4. The relationship cannot be determined from the information given.

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

If one man completes one unit of work, one woman completes half a unit. Thus, 5 men and 5 women equal 7.5 men. The required time is (10 x 12 x 8) / (7.5 x 10) = 12.8 days, which is less than 13 days.

Multiple choice
  1. Quantity A is greater than quantity B.

  2. Quantity B is greater than quantity A.

  3. Both quantities are equal.

  4. The relationship between the quantities cannot be determined.

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Quantity A: 1/20 + 1/24 + 1/30 = (6+5+4)/120 = 15/120 = 1/8. Time = 8 days. Quantity B: B takes 24 days for the whole work, so 1/3 of the work takes 24/3 = 8 days. Both are 8 days.