Time and Work Questions

Multiple choice
  1. $10\ days$
  2. $6\ days$
  3. $8\ days$
  4. $12\ days$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Total work = 16 * 16 = 256 man-days. Work done in 4 days = 16 * 4 = 64 man-days. Remaining work = 256 - 64 = 192 man-days. New number of men = 16 + 8 = 24. Days to complete remaining work = 192 / 24 = 8 days.

Multiple choice
  1. $120$
  2. $90$
  3. $110$
  4. $100$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done = 5km in 9 days with 100 men. Remaining work = 7km in 6 days. Using M1D1/W1 = M2D2/W2: (100 * 9) / 5 = (M2 * 6) / 7. 180 = (M2 * 6) / 7, so M2 = 210. Additional men = 210 - 100 = 110.

Multiple choice
  1. $130$
  2. $125$
  3. $128$
  4. $135$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Calculate man-hours: A = 20*8*6 = 960. B = 15*9*7 = 945. C = 10*6*8 = 480. Total = 960 + 945 + 480 = 2385. C's share = (480 / 2385) * 636 = 128.

Multiple choice
  1. $22\dfrac { 2 }{ 7 } days$
  2. $25\dfrac { 1 }{ 2 } days$
  3. $5\dfrac { 1 }{ 7 } days$
  4. $12 \dfrac { 7 }{ 22 } days$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let M and W be the daily work of a man and woman. 6(4M + 3W) = 1 (total work) => 24M + 18W = 1. 4(5M + 7W) = 1 => 20M + 28W = 1. Solving these, 4M = 10W => M = 2.5W. Substituting, 24(2.5W) + 18W = 1 => 78W = 1 => W = 1/78. Then M = 2.5/78 = 5/156. 1 man + 1 woman = 5/156 + 2/156 = 7/156. Time = 156/7 = 22 2/7 days.

Multiple choice
  1. $2$ days
  2. $4$ days
  3. $6$ days
  4. $8$ days
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

16 men = 12 days, so 1 man = 192 days. 24 children = 18 days, so 1 child = 432 days. Daily work of 1 man = 1/192, 1 child = 1/432. 12 men + 8 children = 12/192 + 8/432 = 1/16 + 1/54 = 35/432. In 8 days, they do 8 * 35/432 = 35/54. Remaining work = 19/54. New force = 12 men + 11 children = 12/192 + 11/432 = 1/16 + 11/432 = 38/432 = 19/216. Days = (19/54) / (19/216) = 4 days.

Multiple choice
  1. $A$
  2. $B$
  3. $C$
  4. Data inadequate

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Given (A+B)=1/5, (B+C)=1/7, (A+C)=1/4. Adding these gives 2(A+B+C) = 1/5+1/7+1/4 = 83/140, so (A+B+C) = 83/280. Subtracting (B+C) gives A = 83/280 - 40/280 = 43/280. Subtracting (A+C) gives B = 83/280 - 70/280 = 13/280. Subtracting (A+B) gives C = 83/280 - 56/280 = 27/280. Since A has the largest work rate (43/280), A takes the least time.

Multiple choice
  1. $40$ days
  2. $20$ days
  3. $35$ days
  4. $70$ days
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let M be the work of a man and B be the work of a boy. 14(3M + 4B) = 10(4M + 6B) => 42M + 56B = 40M + 60B => 2M = 4B => M = 2B. Total work = 14(3(2B) + 4B) = 14(10B) = 140B. Time for one man = 140B / M = 140B / 2B = 70 days.

Multiple choice
  1. $22$ days
  2. $\displaystyle21\frac{1}{2}$days
  3. $23$ days
  4. $\displaystyle22\frac{1}{2}$days
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work rates: A=1/25, B=1/20, C=1/24. Work done in 2 days by A, B, C: 2 * (1/25 + 1/20 + 1/24) = 2 * (24+30+25)/600 = 79/300. Remaining work = 221/300. C works for 43/5 days: 43/5 * 1/24 = 43/120. Remaining = 221/300 - 43/120 = (442-215)/600 = 227/600. A+D+C work for 3 days: 3 * (1/25 + 1/24 + 1/D) = 227/600. Solving for D gives 22.5 days.