Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
B
Correct answer
Explanation
P's rate = 1/12. (P+Q)'s rate = 1/8. Q's rate = 1/8 - 1/12 = 3/24 - 2/24 = 1/24. Q takes 24 days.
C
Correct answer
Explanation
Using the formula M1*D1 = M2*D2. 20 * 20 = 25 * D2. 400 = 25 * D2. D2 = 400 / 25 = 16.
-
$12$
-
$\displaystyle \frac{1}{12}$
-
$\displaystyle \frac{1}{24}$
-
$24$
-
$55.66$
-
$56.44$
-
$56.66$
-
$54.66$
-
$12$ days
-
$15$ days
-
$20$ days
-
$30$ days
B
Correct answer
Explanation
Let B take x days, A takes x/3 days. x - x/3 = 10. 2x/3 = 10. x = 15 days.
-
$10\ days$
-
$6\ days$
-
$8\ days$
-
$12\ days$
C
Correct answer
Explanation
Total work = 16 * 16 = 256 man-days. Work done in 4 days = 16 * 4 = 64 man-days. Remaining work = 256 - 64 = 192 man-days. New number of men = 16 + 8 = 24. Days to complete remaining work = 192 / 24 = 8 days.
C
Correct answer
Explanation
Work done = 5km in 9 days with 100 men. Remaining work = 7km in 6 days. Using M1D1/W1 = M2D2/W2: (100 * 9) / 5 = (M2 * 6) / 7. 180 = (M2 * 6) / 7, so M2 = 210. Additional men = 210 - 100 = 110.
C
Correct answer
Explanation
Calculate man-hours: A = 20*8*6 = 960. B = 15*9*7 = 945. C = 10*6*8 = 480. Total = 960 + 945 + 480 = 2385. C's share = (480 / 2385) * 636 = 128.
B
Correct answer
Explanation
Work done = 36 men * 16 days = 576 man-days for 2/3 of work. Total work = 576 * (3/2) = 864 man-days. Remaining work = 1/3 of total = 288 man-days. New men = 36 + 12 = 48. Days = 288 / 48 = 6 days.
-
$22\dfrac { 2 }{ 7 } days$
-
$25\dfrac { 1 }{ 2 } days$
-
$5\dfrac { 1 }{ 7 } days$
-
$12 \dfrac { 7 }{ 22 } days$
A
Correct answer
Explanation
Let M and W be the daily work of a man and woman. 6(4M + 3W) = 1 (total work) => 24M + 18W = 1. 4(5M + 7W) = 1 => 20M + 28W = 1. Solving these, 4M = 10W => M = 2.5W. Substituting, 24(2.5W) + 18W = 1 => 78W = 1 => W = 1/78. Then M = 2.5/78 = 5/156. 1 man + 1 woman = 5/156 + 2/156 = 7/156. Time = 156/7 = 22 2/7 days.
-
$2$ days
-
$4$ days
-
$6$ days
-
$8$ days
B
Correct answer
Explanation
16 men = 12 days, so 1 man = 192 days. 24 children = 18 days, so 1 child = 432 days. Daily work of 1 man = 1/192, 1 child = 1/432. 12 men + 8 children = 12/192 + 8/432 = 1/16 + 1/54 = 35/432. In 8 days, they do 8 * 35/432 = 35/54. Remaining work = 19/54. New force = 12 men + 11 children = 12/192 + 11/432 = 1/16 + 11/432 = 38/432 = 19/216. Days = (19/54) / (19/216) = 4 days.
-
$A$
-
$B$
-
$C$
-
Data inadequate
A
Correct answer
Explanation
Given (A+B)=1/5, (B+C)=1/7, (A+C)=1/4. Adding these gives 2(A+B+C) = 1/5+1/7+1/4 = 83/140, so (A+B+C) = 83/280. Subtracting (B+C) gives A = 83/280 - 40/280 = 43/280. Subtracting (A+C) gives B = 83/280 - 70/280 = 13/280. Subtracting (A+B) gives C = 83/280 - 56/280 = 27/280. Since A has the largest work rate (43/280), A takes the least time.
-
$40$ days
-
$20$ days
-
$35$ days
-
$70$ days
D
Correct answer
Explanation
Let M be the work of a man and B be the work of a boy. 14(3M + 4B) = 10(4M + 6B) => 42M + 56B = 40M + 60B => 2M = 4B => M = 2B. Total work = 14(3(2B) + 4B) = 14(10B) = 140B. Time for one man = 140B / M = 140B / 2B = 70 days.
-
$22$ days
-
$\displaystyle21\frac{1}{2}$days
-
$23$ days
-
$\displaystyle22\frac{1}{2}$days
D
Correct answer
Explanation
Work rates: A=1/25, B=1/20, C=1/24. Work done in 2 days by A, B, C: 2 * (1/25 + 1/20 + 1/24) = 2 * (24+30+25)/600 = 79/300. Remaining work = 221/300. C works for 43/5 days: 43/5 * 1/24 = 43/120. Remaining = 221/300 - 43/120 = (442-215)/600 = 227/600. A+D+C work for 3 days: 3 * (1/25 + 1/24 + 1/D) = 227/600. Solving for D gives 22.5 days.
C
Correct answer
Explanation
This is an inverse proportion problem. 15 men * 3 days = 45 man-days. 9 men * x days = 45 man-days. x = 45 / 9 = 5 days.