Multiple choice

P and Q together can complete a work in 6 days. Q and R together can complete the same work in 15 days. P and R together can complete the work in 20/3 days. What is the ratio of number of days that Q alone takes to complete the work to the number of days that R alone takes to complete the work?

  1. 1:3

  2. 3:5

  3. 3:1

  4. 4:5

  5. 5:7

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation