Multiple choice

Three men can do a piece of work in six days. 4 women can finish the same piece of work in nine days, whereas 9 children can complete the same work in five days. 2 men, 6 women and 10 children work for 1 day. If the remaining work has to be completed the next day only by men, then how many men would be required to complete the work?

  1. 8

  2. 9

  3. 12

  4. 18

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
AI explanation

Assume the least common multiple of the days is the total work, so total work is 90 units. The daily work of one man is 5 units, one woman is 2.5 units, and one child is 2 units. The work done by 2 men, 6 women, and 10 children in one day is (10 + 15 + 20) = 45 units, leaving 45 units of remaining work. To finish the 45 remaining units in one day, the number of men required is 45 / 5, which is 9 men.