Time and Work Questions

Multiple choice
  1. 12

  2. 10

  3. 9

  4. 8

  5. None of these इनमे से कोई नही

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

16 men's 1 day work = 1/30, so 1 man's 1 day work = 1/480. 18 women's 1 day work = 1/32, so 1 woman's 1 day work = 1/576. Let 5 men + 12 women work together for d days. Work done = d(5/480 + 12/576) = d(1/96 + 1/48) = d(3/96) = d/32. Remaining work = 1 - d/32, done by 12 women in 36 days: (1 - d/32) = 36 × 12/576 = 36/48 = 3/4. So d/32 = 1/4, giving d = 8. Option D is correct.

Multiple choice
  1. If the data in statement II alone is sufficient to answer the question

  2. If the data in both statements I and II together is sufficient to answer the question

  3. If the data either in statement I and III is sufficient to answer the question

  4. If the data either in statement II alone or I and III are sufficient to answer the question

  5. Any two of them together are sufficient

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Statement I: Man builds in 20 days, woman in 24 days. Combined work: 1/20 + 3/24 = 1/20 + 1/8 = 12/240 + 30/240 = 42/240 = 7/40 wall per day. But we don't know wall length. Statement II: Man builds half in 10 days (so full in 20 days, consistent with I). Woman builds 1/3 in 8 days (so full in 24 days, consistent). Also: 1 man-day = 6 meters. So 20 man-days = 120 meters (wall length). 2 men + 3 women in 1 day: 2×6 + 3×(120/24) = 12 + 15 = 27 meters. Statement III: All 5 workers build 27 meters in 1 day. With I & III: We know rates but not length. With II alone: Complete info. With I & III: We have work rates and total output but not individual lengths unless combined with II. Actually, II alone or I & III both work. Option D is correct.

Multiple choice
  1. Any one of them

  2. Either A or C

  3. Only B

  4. Any two of them

  5. All A, B and C together are required

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Any two statements provide sufficient information. A gives work rate of a combined group. B gives relative efficiency of men and women. C gives work rate of men alone. Any pair allows determining individual rates, then calculating time for remaining work.

Multiple choice
  1. 24 days

  2. 18 days

  3. 12 days

  4. 36 days

  5. None of these इनमे से कोई नही

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let A's usual efficiency = a, B's usual efficiency = b. Total work = 12(a + b). With changed efficiencies: A works at 0.5a, B works at 3b. They finish in 9 days: 9(0.5a + 3b) = 12(a + b). Simplifying: 4.5a + 27b = 12a + 12b, giving 15b = 7.5a, so a = 2b. Total work = 12(a + 2a) = 36a. Time for A alone = 36a/a = 36 days. Wait, let me recalculate: If a = 2b, then original: 12(2b + b) = 36b. Changed: 9(0.5 × 2b + 3b) = 9(b + 3b) = 36b. This matches. A alone at efficiency 2b completes 36b work in 36b/2b = 18 days.

Multiple choice
  1. 8

  2. 6

  3. 5

  4. 10

  5. None of these इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work equations: 4M×12 = 6W×10 → 48M = 60W → M = 5W/4. 4M×12 = 8C×9 → 48M = 72C → M = 3C/2. Equating: 5W/4 = 3C/2 → W = 6C/5. Given M+W+C = 10 days → 1/10 work per day combined. Substituting in terms of C: (3C/2) + (6C/5) + C = (15C+12C+10C)/10 = 37C/10 per 10 days = 37C/100 per day. So 37C/100 = 1/10 → C = 10/37. We need 2W+5C: 2×(6C/5) + 5C = 12C/5 + 5C = 37C/5 = 37/5 × 10/37 = 2. So 2W+5C do 2/10 work per day = 1/5 job per day. Time = 5 days. Option C is correct.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity II > Quantity I

  4. Quantity II ≥ Quantity I

  5. Quantity I = Quantity II or Relation cannot be established

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Quantity I: Let C's time = x days. B takes x/2 days, A takes x/1.5 days. Combined rate: 1/x + 2/x + 1.5/x = 4.5/x = 1/6, so x = 27 days for C. Quantity II: 30 × 16 = 480 man-days work. After 6 days: 30 × 6 = 180 done, 300 remain. With 50 men: 300/50 = 6 more days. Quantity I (27) > Quantity II (6). Option A is correct.

Multiple choice
  1. 22 days

  2. 25 days

  3. 33 days

  4. 28 days

  5. None of these इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let Kartik's rate = K. Akhil does 2× work in 1/6 time, so Akhil's rate = 12K. Sandeep is 25% less efficient: rate = 9K. Together: K + 12K + 9K = 22K. 22K = 1/12, so K = 1/264. Kartik doubled: 2K = 1/132. Akhil halved: 6K = 1/44. New combined rate = 1/132 + 1/44 = 4/132 = 1/33. Time = 33 days. Option C is correct.

Multiple choice
  1. Rs 3200 3200 रुपये

  2. Rs 10400 10400 रुपये

  3. Rs 4200 4200 रुपये

  4. Rs 3600 3600 रुपये

  5. None of these इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work ratio 5:3:1 means 9 total work units. 20 men × 5 = 100 units, 24 women × 3 = 72 units, 40 children × 1 = 40 units. Total = 212 units worth ₹1484. Each unit = ₹7. Men's share = (100/212) × 1484 = ₹700, so each man gets ₹35. Women's share = (72/212) × 1484 = ₹504, each woman gets ₹21. Children's share = (40/212) × 1484 = ₹280, each child gets ₹7. For 12 men, 20 women, 30 children: 12×35 + 20×21 + 30×7 = 420 + 420 + 210 = ₹1050. For 4 weeks: 1050 × 4 = ₹4200.

Multiple choice
  1. 1 day 1 दिन

  2. 3 days 3 दिन

  3. 2 days 2 दिन

  4. 4 days 4 दिन

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

4 men's work rate = 1/2 per day, so 1 man = 1/8 per day. 4 women = 1/4 per day, so 1 woman = 1/16 per day. 5 children = 1/4 per day, so 1 child = 1/20 per day. Combined work of 2 men + 4 women + 10 children = 2(1/8) + 4(1/16) + 10(1/20) = 1/4 + 1/4 + 1/2 = 1. So they complete 1 work per day = 1 day. Option A correctly states 1 day. Options B, C, D overestimate.

Multiple choice
  1. Quantity II < Quantity I मात्रा II < मात्रा I

  2. Quantity II > Quantity I मात्रा II > मात्रा I

  3. Quantity II ≤ Quantity I मात्रा II ≤ मात्रा I

  4. Quantity II ≥ Quantity I मात्रा II ≥ मात्रा I

  5. Quantity II = Quantity I or relation cannot be established मात्रा II = मात्रा I या संबंध स्थापित नहीं किया जा सकता है

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Quantity I: From work rates: A+B = 1/8, B+C = 1/12, C+A = 1/8. Adding first and third: 2A + B + C = 1/4. Subtracting second: 2A = 1/4 - 1/12 = 1/6, so A = 1/12. Time for A alone = 12 days. Quantity II: (A+B)×6 + B×24 = 1. 6A + 30B = 1. Also A+B = 1/18, so A = 1/18 - B. Solving: 6(1/18 - B) + 30B = 1, giving 1/3 + 24B = 1, B = 1/36. Then A = 1/18 - 1/36 = 1/36. Time for A alone = 36 days. Quantity II (36) > Quantity I (12).

Multiple choice
  1. 3 days 3 दिन

  2. 2 days 2 दिन

  3. 1 days 1 दिन

  4. 4 days 4 दिन

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work completed: 8 plumbers × 7 hours × 3 days = 168 plumber-hours for 84 taps. Each tap needs 168/84 = 2 plumber-hours. Remaining work: 182 - 84 = 98 taps requiring 98 × 2 = 196 plumber-hours. With 7 plumbers working 7 hours daily: 7 × 7 = 49 plumber-hours per day. Days needed = 196/49 = 4 days.

Multiple choice
  1. 5

  2. 6

  3. 7

  4. 8

  5. 9

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Man's rate = 1/11 work per day. Days 1-8: men increase from 1 to 8. Days 9 onwards: 8 men work constantly. For 4× work: First 8 days complete sum(1 to 8)/11 = 36/11 units. Remaining: 4 - 36/11 = 8/11 units. With 8 men: (8/11)/(8/11) = 1 day. Total = 8 + 1 = 9 days. Option E is correct. The key insight is that after day 8, the workforce stabilizes at 8 men.

Multiple choice
  1. If statement I alone is sufficient but statement II alone is not sufficient. यदि केवल कथन I ही पर्याप्त है लेकिन केवल कथन II पर्याप्त नहीं है

  2. If statement II alone is sufficient but statement I alone is not sufficient. यदि केवल कथन II ही पर्याप्त है लेकिन केवल कथन I पर्याप्त नहीं है

  3. If each statement alone (either I or II) is sufficient. यदि या केवल कथन I या केवल II पर्याप्त हैं

  4. If statement I and II together are not sufficient. यदि कथन I व II दोनों अपर्याप्त हैं

  5. If both statements I and II together are sufficient, but neither statement alone is sufficient. यदि दोनों कथन I व II एक साथ पर्याप्त हैं लेकिन अलग-अलग पर्याप्त नहीं हैं

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Statement I: 3M + 4W complete work in 16 days. Statement II: 6M + 8W complete work in 12 days. Notice that 6M + 8W = 2(3M + 4W), so the second group has exactly twice the workers. If 3M + 4W take 16 days, then 6M + 8W should take 8 days, not 12 days. This inconsistency means the data is contradictory. Therefore, both statements together are insufficient.

Multiple choice
  1. 108

  2. 72

  3. 54

  4. 60

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Total payment distribution: Anchal gets half (10800/2=5400), Ranjeet gets one-third (10800/3=3600), Vijay gets remainder (10800-5400-3600=1800). Payment ratio A:R:V = 5400:3600:1800 = 3:2:1. In work problems, payment is proportional to work rate. If A, R, V together finish in 36 days, their combined rate = 1/36 work per day. With ratio 3:2:1, individual rates: A=3k, R=2k, V=k. Combined: 6k=1/36, so k=1/216. A and V together: 3k+k=4k=4/216=1/54. Time = 1/(1/54) = 54 days.

Multiple choice

Which information is/are sufficient to answer the questions asked? 40 men and 30 women are working together in a field. After working for 5 days, 10 men and 20 women leave the work. How many more days will be required to complete the remaining work? I. 20 men and 15 women together can complete the work in 7.5 days. II. 15 men and 75 women can complete half work in 1.6 days. III. In a day, the work done by four men is equal to the work done by five women. पूछे गए प्रश्नों का उत्तर देने के लिए कौन सी जानकारियाँ पर्याप्त हैं? एक खेत में 40 पुरुष और 30 महिलाएं मिलकर काम कर रहे हैं। 5 दिनों तक काम करने के बाद, 10 पुरुष और 20 महिलाएं काम छोड़ देती हैं। शेष काम को पूरा करने के लिए कितने दिन की आवश्यकता होगी? I. 20 पुरुष और 15 महिलाएं 7.5 दिनों में काम पूरा कर सकती हैं। II. 15 पुरुष 75 महिलाएं आधे काम को 1.6 दिनों में पूरा कर सकते हैं। III. एक दिन में, चार पुरुषों द्वारा किया गया काम पांच महिलाओं द्वारा किए गए काम के बराबर है।

  1. Any two of the three together are sufficient तीन में से कोई दो एकसाथ पर्याप्त हैं

  2. II and III only केवल II और III

  3. I or II only केवल I या II

  4. III and II or III I या II या III

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

To solve this, we need the work rates of men and women. Any two statements give us enough information: I+II gives two independent equations, I+III or II+III let us substitute the ratio from III into the rate equation from I or II. All three pairs lead to a unique solution.