Time and Work Questions

Multiple choice
  1. 6 days

  2. 7 days

  3. 9 days

  4. 8 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Asha completes 1/6 of work per day, Bhuvan completes 1/9 per day. They work alternately starting with Asha. Day 1-6 (3 cycles): Asha does 3/6=1/2, Bhuvan does 3/9=1/3. Total after 6 days = 1/2+1/3=5/6. Remaining work = 1/6. Day 7 (Asha's turn): She needs 1 day for her 1/6 portion, but only 1/6 remains. So she completes it in 1/6 ÷ (1/6) = 1 day. Total = 7 days. Option B is correct. Option A(6 days) is too early, C(9 days) and D(8 days) are too late.

Multiple choice
  1. 18

  2. 12

  3. 24

  4. 16

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

In 1 day, Anshu completes 1/9 of the work, Swati completes 1/12, and together with Rajni they complete 1/4. Therefore, Rajni's daily work rate is 1/4 - 1/9 - 1/12 = 1/18, which means she alone would take 18 days to complete the work.

Multiple choice
  1. 72

  2. 56

  3. 64

  4. 36

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let m be man's 1-day work and w be woman's 1-day work. From given: 5m + 8w = 1/34 and 4m + 18w = 1/28. Solving: m = 2/170, w = 3/170. For 3 men and 5 women: 3m + 5w = 3(2/170) + 5(3/170) = 21/170. Days needed: 170/21 ≈ 8, so 170/21 × 7 = 56 days. Option B is correct.

Multiple choice
  1. 10 days 10 दिन

  2. 12 days 12 दिन

  3. 15 days 15 दिन

  4. 18 days 18 दिन

  5. 24 days 24 दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

P does 2/5 work in 12 days, so P's full work time = 12 × 5/2 = 30 days. Q does 3/4 work in 15 days, so Q's full work time = 15 × 4/3 = 20 days. Together in 1 day: 1/30 + 1/20 = 5/60 = 1/12, so they complete the work in 12 days.

Multiple choice
  1. 32

  2. 30

  3. 26

  4. 28

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = 12 women × 52 days = 624 woman-days. (2/3) of work = 624 × (2/3) = 416 woman-days. Women needed = 416 ÷ 13 = 32 women. Use inverse proportion: more work in less time requires more workers.

Multiple choice
  1. Rs. 5000

  2. Rs. 3000

  3. Rs. 4500

  4. Rs. 4800

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

P:Q efficiency = 2:3, Q:R = 4:5. Combined P:Q:R = 8:12:15. P completes project in 30 days, so P's efficiency = 1/30. Let total work = 1. P's share = 8/35 of work. Payment is Rs.700/day per efficiency unit. R's efficiency = 15/8 × P = 15/8 × 1/30 = 1/16. R works for 16 days earning 16×700×(15/35) = Rs.4800.

Multiple choice
  1. 80 days

  2. 70 days

  3. 50 days

  4. 45 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Volume1 = 150×20×12 = 36000. Volume2 = 800×15×6 = 72000 (double). Worker-hours1 = 16×6×25 = 2400. Worker-hours2 = 12×8×d. Using chain rule: 36000/2400 = 72000/(96d). Solving gives d = 50.

Multiple choice
  1. 12

  2. 8

  3. 6

  4. 10

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 30 persons × 10 days × 8 hours/day = 2400 person-hours. This same work must be completed by 40 persons in 6 days. Let h be hours per day. Then 40 × 6 × h = 2400, so 240h = 2400, giving h = 10 hours per day. This is an inverse variation problem - more people means fewer hours needed.

Multiple choice
  1. 12 days

  2. 9 days

  3. 10 days

  4. 8 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A does 2/5 work in 6 days, so rate = 1/15 per day. B does 2/3 work in 12 days, so rate = 1/18 per day. Together they do 11/90 per day. In 6 days: 44/90 done, 46/90 left. C does 46/90 in 8 days, so C's rate = 23/360 per day. A + C together: 1/15 + 23/360 = 47/360 per day, so time = 360/47 ≈ 7.66 days, which rounds to 8 days. The answer is correct.

Multiple choice
  1. 80

  2. 45

  3. 36

  4. 49

  5. 60

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let total work = 1 unit, combined efficiency = 6+4+5=15 units/day. Estimated days = 1/15. With R's 60% evening destruction, net daily work = 15 - 60% of 5 = 12 units. Actual days = 1/12. Given actual = estimated + 20 days: 1/12 - 1/15 = 20. Solving: (5-4)/60 = 20, so 1/60 = 20, giving estimated days = 80. The key is recognizing that 20 extra days come from reduced net efficiency.