Time and Work Questions

Multiple choice
  1. $23.389 days$
  2. $23.365 days$
  3. $23.356 days$
  4. $23.322 days$
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Efficiencies 2.5:3.5:5.5 means work rates are proportional to these values. Combined rate = 11.5k, completing work in 13 days. A's rate = 2.5k. A alone would take 13 × 11.5/2.5 = 59.8 days for full work. For 39% of work: 59.8 × 0.39 ≈ 23.322 days.

Multiple choice
  1. 20

  2. 24

  3. 27

  4. 25

  5. 30

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Total work = 15×21×8 = 2520 man-hours. 3 women = 2 men, so 1 woman = 2/3 man. 21 women = 21×(2/3) = 14 men. Let days = d. 14×d×6 = 2520. 84d = 2520. d = 30 days.

Multiple choice
  1. 8

  2. 3

  3. 15

  4. 10

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 40 × 15 = 600 man-days. New time = 12 days. Men needed = 600/12 = 50. Additional men = 50 - 40 = 10.

Multiple choice
  1. Quantity : I > Quantity : II

  2. Quantity : I ≥ Quantity : II

  3. Quantity : I < Quantity : II

  4. Quantity : II ≥ Quantity : I

  5. Quantity I = Quantity II or relation can't be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

24 men complete work in 20 days, so 1 man's 1 day work = 1/(24*20). 15 men's 1 day work = 15/(24*20) = 1/32, so time = 32 days. 36 women complete in 24 days, so 1 woman's 1 day work = 1/(36*24). 16 women's 1 day work = 16/(36*24) = 1/54, so time = 54 days. Quantity I (32 days) < Quantity II (54 days).

Multiple choice
  1. 7 days

  2. 5 days

  3. 3 days

  4. 6 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = LCM(10,12,15) = 60 units. Rates: A = 6, B = 5, C = 4 units/day. All work together for 2 days: 15 × 2 = 30 units done, 30 left. B leaves 3 days before completion, so B works 4 days total (2 + 4 = 6 total work duration): B does 5 × 4 = 20 units. Remaining 40 units done by A and C at 10 units/day = 4 days. Total = 2 + 4 = 6 days... Wait, let me recalculate: Days 1-2: all three work (30 done). Days 3-4: B and C work (20 done, 50 total). Days 5-7: only C works (12 done, 62 total - exceeds 60). This doesn't work. Correct approach: Let total days = d. A works 2 days, B works (d-3) days, C works d days. 6×2 + 5×(d-3) + 4×d = 60. 12 + 5d - 15 + 4d = 60. 9d - 3 = 60. 9d = 63. d = 7.

Multiple choice
  1. Rs 150

  2. Rs 100

  3. Rs 180

  4. Rs 220

  5. None of these

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Let total wages for men, women, children be 18x, 10x, 12x. Total = 40x = 4000, so x = 100. Women's total = 1000. Individual wages are 6k, 5k, 3k. Total people = 18x/(6k) + 10x/(5k) + 12x/(3k) = 900/k = 18, so k = 50. One woman earns 5k = Rs 250. Since 250 is not in options, answer is None of these (option E).

Multiple choice
  1. 35 days 35 दिन

  2. 40 days 40 दिन

  3. 25 days 25 दिन

  4. 20 days 20 दिन

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

12 men = 20 women can do work in 54 days. 1 man = 20/12 = 5/3 women. 9 men + 12 women = 9×(5/3) + 12 = 15 + 12 = 27 women. 20 women take 54 days, so 27 women take 54×20/27 = 54×20/27 = 40 days.

Multiple choice
  1. Quantity : I > Quantity : II

  2. Quantity : I ≥ Quantity : II

  3. Quantity : I < Quantity : II

  4. Quantity : II ≥ Quantity : I

  5. Quantity I = Quantity II or relation can't be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Anay completes half work in 18 days, so full work in 36 days (rate = 1/36). Meera's rate = 1/30. Combined rate = 1/36 + 1/30 = 11/180, so together they complete work in 180/11 ≈ 16.36 days. Quantity II: Anay works 3 days (3/36 = 1/12 work done), remaining 11/12 by both at 11/180 rate = 15 days. Total = 3 + 15 = 18 days. Since 16.36 < 18, Quantity I < Quantity II.

Multiple choice
  1. 20

  2. 28

  3. 30

  4. 21

  5. 25

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Efficiency ratio 2:5:7 means total efficiency units = 2+5+7 = 14. Working together, they complete the work in 10 days, so total work = 14 × 10 = 140 units. A's efficiency is 2 units/day, so A alone would take 140/2 = 70 days to complete the full work. For 30% of work (0.3 × 140 = 42 units), A would take 42/2 = 21 days. Option D is correct.

Multiple choice
  1. 100: 63

  2. 63: 100

  3. 4 :7

  4. 13 :15

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

14 men complete the work in 15 days, so 1 man's 1-day work = 1/210. 15 women complete in 20 days, so 1 woman's 1-day work = 1/300. Work by 20 men in 1 day = 20/210 = 2/21. Work by 18 women in 1 day = 18/300 = 3/50. The ratio is (2/21) : (3/50) = 100 : 63.

Multiple choice
  1. 22 days 22 दिन

  2. 24 days 24 दिन

  3. 20 days 20 दिन

  4. 25 days 25 दिन

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A + B = 1/12 work/day, B + C = 1/16 work/day. Work done: A worked 5 days, B worked 7 days, C worked 13 days. So 5A + 7B + 13C = 1 (complete work). Substituting A = 1/12 - B and C = 1/16 - B: 5(1/12 - B) + 7B + 13(1/16 - B) = 1. Solving: 5/12 + 13/16 + (7 - 5 - 13)B = 1. This gives -11B = 1 - 5/12 - 13/16 = -11/48, so B = 1/48. Then C = 1/16 - 1/48 = 1/24. So C alone takes 24 days.

Multiple choice
  1. 64days

  2. 32days

  3. 28days

  4. 54days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

First find the work: 2 men × 15 days × 8 hours = 240 man-hours. Same work done by 3 women × 16 days × 4 hours = 192 woman-hours. So 240 man-hours = 192 woman-hours, meaning 1 man = 0.8 woman or 1 woman = 1.25 men. Boy's efficiency is 50% more than woman, so 1 boy = 1.5 women = 1.5 × 1.25 = 1.875 men. Time = 240 / (1.875 × 2) = 64 days.

Multiple choice
  1. 10

  2. 40

  3. 30

  4. 20

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

30 men × 100 days = 3000 man-days required. In 25 days with 30 men: 30 × 25 = 750 man-days of work capacity, but only 20% (600 man-days) of work was completed. This means efficiency = 600/750 = 0.8 or 80%. Remaining work = 80% × 3000 = 2400 man-days. Remaining days = 100 - 25 = 75 days. At 80% efficiency, effective capacity = 75 × 0.8 = 60 man-days/day equivalent. Men needed = 2400/60 = 40 men. Increase = 40 - 30 = 10 men.

Multiple choice
  1. 44 days 44 दिन

  2. 45 days 45 दिन

  3. 42 days 42 दिन

  4. 48 days 48 दिन

  5. 50 days 50 दिन

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let total work = 1 unit. A's rate = 1/x and B's rate = 1/(x+32). Together their rate = 1/x + 1/(x+32). In 6 days they complete 20% (0.2) of work: 6(1/x + 1/(x+32)) = 0.2. Solving: 6(x+32 + x)/x(x+32) = 0.2, so 12x + 192 = 0.2x² + 6.4x. Rearranging: 0.2x² - 5.6x - 192 = 0, or x² - 28x - 960 = 0. Using quadratic formula: x = [28 ± √(784 + 3840)]/2 = [28 ± √4624]/2 = [28 ± 68]/2. So x = 48 (positive root). A alone takes 48 days.