Multiple choice

12 women can complete a work in 52 days, then find how many women will be required to complete (2/3)rd of the same work in 13 days? 12 महिलाएं एक कार्य को 52 दिनों में पूरा कर सकती हैं, तो ज्ञात कीजिए कि उसी कार्य का (2/3) भाग 13 दिनों में पूरा करने के लिए कितनी महिलाओं की आवश्यकता होगी?

  1. 32

  2. 30

  3. 26

  4. 28

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = 12 women × 52 days = 624 woman-days. (2/3) of work = 624 × (2/3) = 416 woman-days. Women needed = 416 ÷ 13 = 32 women. Use inverse proportion: more work in less time requires more workers.