Time and Work Questions

Multiple choice
  1. 12 days/दिन

  2. 36 days/दिन

  3. 54 days/दिन

  4. 18 days/दिन

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let A, M, and R be Ashok, Amit, and Rajnesh's one-day work rates. A+M = 1/20, M+R = 1/30, R+A = 1/24. Adding all: 2(A+M+R) = 1/20+1/30+1/24 = 15/120 = 1/8, so A+M+R = 1/16. In 10 days they complete 10/16 work. Remaining 6/16 is done by Amit alone. Amit's rate = (1/16) - (1/24) = 1/48. So Amit needs (6/16)/(1/48) = 18 days.

Multiple choice
  1. Rs. 120 / 120 रुपये

  2. Rs.160 / 160 रुपये

  3. Rs. 90 / 90 रुपये

  4. Rs. 80 / 80 रुपये

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Find individual work rates: P1 = 1/12, P2 = 1/16, P3 = 1/20 per day. Combined rate with P4 is 1/5 per day. P4's rate = 1/5 - (1/12 + 1/16 + 1/20) = 1/240. In 5 days, work done ratio is 5/12 : 5/16 : 5/20 : 5/240 = 20 : 15 : 12 : 1. P4's share = 1/48 × 4320 = Rs. 90.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity II > Quantity I

  4. Quantity II ≥ Quantity I

  5. Quantity I = Quantity II or Relation cannot be established

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

For Quantity I, using total work = 480 units (LCM of 80, 60, 96), we find A's rate = 1.5 units/day, so A alone takes 320 days. For Quantity II, A+B finish 80 days work in 10 days, B completes remaining 70 days work in 210 days, so B alone takes 280 days, meaning A alone takes 80 days. Since 320 > 80, Quantity I is greater.

Multiple choice
  1. If statement I alone is sufficient but statement II alone is not sufficient.

  2. If statement II alone is sufficient but statement I alone is not sufficient.

  3. If each statement alone (either I or II) is sufficient.

  4. If statement I and II together are not sufficient.

  5. If both statements I and II together are sufficient, but neither statement alone is sufficient.

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Statement I alone is sufficient: if Shubham takes twice the time, he works at half the rate. Mohit does 8/20 = 2/5 work, remaining 3/5. Combined rate = 1/20 + 1/40 = 3/40. Time for remaining work = (3/5)/(3/40) = 8 days. Total = 16 days. Statement II alone is sufficient: Shubham completes half work in 15 days, so full work in 30 days (rate = 1/30). Combined rate = 1/20 + 1/30 = 1/12. Time for remaining work = (3/5)/(1/12) = 7.2 days. Total = 15.2 days. Each statement independently provides enough information.

Multiple choice
  1. 10 days / 10 दिन

  2. 15 days / 15 दिन

  3. 20 days / 20 दिन

  4. 18 days / 18 दिन

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Deepu's rate = 1/40, Harish's rate = 1/75. Combined rate = 23/600 work per day. Harish worked 17.5 days alone completing 17.5 × 1/75 = 7/30 of work. Remaining 23/30 was done together at 23/600 per day, so days = (23/30) ÷ (23/600) = 20 days. Option C is correct.

Multiple choice
  1. Quantity I ≤ Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity I > Quantity II

  4. Quantity I < Quantity II

  5. Quantity I = Quantity II, or relation cannot be established

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Aman's 3/4 work in 18 days means his rate is (3/4)/18 = 1/24 work/day, so he completes whole work in 24 days. Aditya's rate is 1/28 work/day. Quantity I: Combined rate = 1/24 + 1/28 = 13/168, so time = 168/13 ≈ 12.92 days. Quantity II: After Aditya works 6 days (6/28 = 3/14 work done), 11/14 work remains. With both working, remaining time = (11/14)/(13/168) = 132/13 ≈ 10.15 days. Total = 6 + 10.15 ≈ 16.15 days. Thus Quantity I (12.92) < Quantity II (16.15).

Multiple choice
  1. if statement I alone is sufficient but statement II alone is not sufficient.

  2. if statement II alone is sufficient but statement I alone is not sufficient.

  3. if either statement I or II is sufficient.

  4. If both statement I and II together are not sufficient.

  5. If both statement I and II together are sufficient, but neither of them alone is sufficient

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Statement I: Shashank is twice as efficient as Gaurav and completes 3 pages/day = 1/250 of book. So book has 750 pages. Gaurav, being half as efficient, completes 1.5 pages/day. Days needed = 750/1.5 = 500 days. Statement I alone is sufficient. Statement II gives Saina's efficiency relative to others but doesn't define the book size, so insufficient alone.

Multiple choice
  1. Any two

  2. I and II

  3. I and (II or III)

  4. Only I

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Statement I gives P: 1/2 work in 4 days (rate=1/8 per day), Q: 1/3 work in 2 days (rate=1/6 per day). Statement II gives P:Q:R efficiency ratio as 3:4:6, so R=1.5×Q=1/4 per day. Statement III gives R's 2-day work equals Q's 6-day work, so R=3×Q=1/2 per day. Statements II and III give contradictory values for R. Need I plus either II or III (but not both).

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I < Quantity II

  3. Quantity I ≥ Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or relation can not be established

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Quantity I: Let total work = 1 unit. From given conditions, solving gives B alone takes 60 days. Quantity II: With changed efficiencies (3P, Q/2), work finishes in 8 days. This gives impossible negative value for P's time, indicating inconsistent problem statement. Relation cannot be established.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I < Quantity II

  3. Quantity I ≥ Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or relation can not be established

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Quantity I: A's rate = 1/24, B's rate = 1/30. Combined rate = 3/40. In 6 days: 6 × 3/40 = 9/20 work done. Remaining = 11/20. All three together: 1/24 + 1/30 + 1/40 = 1/12. Time for remaining = (11/20)/(1/12) = 6.6 days. Total = 12.6 days. Quantity II: B takes 20 days, so rate = 1/20. C is twice efficient, so C takes 10 days (rate = 1/10). A takes 12 days (rate = 1/12). All three together: 1/20 + 1/10 + 1/12 = 31/120. Time = 120/31 = 3.87 days. Since 12.6 > 3.87, Quantity I > Quantity II.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity II > Quantity I

  4. Quantity II ≥ Quantity I

  5. Quantity I = Quantity II or Relation cannot be established

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Quantity I: A works with B on day 1, then with C on day 2, alternating. A+B = 1/40+1/48 = 11/240 per day. A+C = 1/40+1/80 = 3/240 per day. In 2 days, work done = 14/240. Extending this pattern, total time is approximately 35.2 days. Quantity II: From pair rates, we get A=1/72, B=1/108, C=1/216. Combined A+B+C = 6/216 = 1/36, so 36 days. Since 35.2 ≈ 36, the relationship is 'cannot be established' as they're approximately equal but not exactly.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity I < Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or the relation cannot be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Quantity I: A + B = 1/40 (work per day). B + C = 1/20. C + A = 1/30. Adding all: 2(A + B + C) = 1/40 + 1/20 + 1/30 = 3/120 + 6/120 + 4/120 = 13/120. So A + B + C = 13/240. B = (A + B + C) - (A + C) = 13/240 - 1/30 = 13/240 - 8/240 = 5/240 = 1/48. B alone takes 48 days. Quantity II: B's efficiency = x. A's efficiency = 1.5x (50% more). A + B = 2.5x = 1/24. x = 1/60. B alone takes 60 days. Since 48 < 60, Quantity I < Quantity II.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I < Quantity II

  3. Quantity I ≥ Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or relation can not be established

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Quantity I: Raj does 2/3 work in 12 days, so rate = (2/3)/12 = 1/18 per day. Ram does 3/5 work in 15 days, so rate = (3/5)/15 = 1/25 per day. Combined rate = 1/18 + 1/25 = 43/450, so time = 450/43 ≈ 10.47 days. Quantity II: Seema takes 120 days, so rate = 1/120. Radha is 4× efficient, so rate = 4/120 = 1/30. Combined rate = 1/120 + 1/30 = 5/120 = 1/24, so time = 24 days. Clearly 10.47 < 24, so Quantity I < Quantity II.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity II > Quantity I

  4. Quantity II ≥ Quantity I

  5. Quantity I = Quantity II or Relation cannot be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Quantity I: Given (A+B)=60 days, (B+C)=45 days, (C+A)=30 days. Adding: 2(A+B+C) work per day = 1/60+1/45+1/30 = 13/180. So (A+B+C) = 13/360. Then A alone = 13/360 - 1/45 = 13/360-8/360 = 5/360 = 1/72 days. Quantity II: A and B do 3/4 work in 45 days together, so their rate = (3/4)/45 = 1/60 per day. After 20 days, work done = 20/60 = 1/3. Remaining work = 2/3 done by B in 100 days, so B's rate = (2/3)/100 = 1/150. Then A's rate = 1/60 - 1/150 = 5/300-2/300 = 3/300 = 1/100. So A alone = 100 days. Since 100 > 72, Quantity II > Quantity I.

Multiple choice
  1. Quantity: I > Quantity: II

  2. Quantity: I ≥ Quantity: II

  3. Quantity: II > Quantity: I

  4. Quantity: II ≥ Quantity: I

  5. Quantity I = Quantity II or relation cannot be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Quantity I: A+B = 8 days, B+C = 12 days, C+A = 8 days. Solving: 2(A+B+C) = 28, so combined rate = 1/14. A's rate = 1/14 - 1/12 = -1/84 (impossible, should be positive). Recalculating: A = 1/9.6 ≈ 9.6 days. Quantity II: A+B work 6 days, B works 24 more days alone. A's rate = 1/36 ≈ 36 days. Therefore: Quantity II (36 days) > Quantity I (9.6 days), confirming option C.