Each question below contains a statement followed by Quantity I and Quantity II. You have to find the correct relationship. Aman can do the three-fourth of the work in 18 days and Aditya can do the whole work in 28 days. Quantity I: In how many days will Aman and Aditya do the whole work? Quantity II: If Aditya starts the work and works for 6 days, after that Aman joins him, in how many days will the whole work be completed?