Quantity I: Working alone, B can complete the work in 20 days. C is twice as efficient as B and A takes 2 days more than it takes C to complete the work. Working together, in how much time would they be able to complete 7 such works? Quantity II: Working alone, A, B and C can do a work in 24, 30 and 40 days respectively. How long will it take them to complete the work if only A and B work for the first 6 days and then C started the work?
Reveal answer
Fill a bubble to check yourself