Quantitative Aptitude

Time, Work, and Projects

198 Questions

Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.

Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers

Time, Work, and Projects Questions

Multiple choice technology testing
  1. 5

  2. 20

  3. 440

  4. 110

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Test effort is measured in person-months, which represents the work done by testers in a month. With 5 testers working for 1 month, the test effort for the first month is 5 person-months. This is simply the number of testers allocated since effort is calculated per month of work.

Multiple choice technology testing
  1. 24.00%

  2. 30%

  3. 32%

  4. 8%

Reveal answer Fill a bubble to check yourself
A Correct answer
Multiple choice technology
  1. 1 Day

  2. 1 week

  3. 8 Days

  4. 3 Days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

CMR scheduling requires advance notice to ensure resource allocation and job preparation. 8 days allows sufficient time for processing, validation, and queue placement. Shorter timeframes (1-3 days) are typically insufficient for proper scheduling procedures.

Multiple choice
  1. 20

  2. 18

  3. 16

  4. 15

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

For skilled: men -> days -> amount of wall

5 -> 20  -> 1
1 -> 100 -> 1
1 -> 1   -> 1/100
For semi-skilled: men -> days -> amount of wall

8 -> 25  -> 1

1 -> 200 -> 1
1 -> 1   -> 1/200
For unskilled: men -> days -> amount of wall

10 -> 30  -> 1

1  -> 300 -> 1
1  -> 1   -> 1/300
Amount of work 2 skilled in 1 day = 2/100 Amount of work 6 semi-skilled in 1 day = 6/200 Amount of work 5 unskilled in 1 day = 5/300

Total work in 1 day 

= 2/100+6/200+5/300
= 12/600+18/600+10/600
= 1/15

So complete work will take 15 days

Multiple choice
  1. 4

  2. 5

  3. 6

  4. 7

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let each truck carry 100 units. 2800 = 4n + e n = normal 3000 = 10n + e e = excess/pending             $\therefore$$ n =\dfrac{100}{3}, e =\dfrac{8000}{3} $             5days $\Rightarrow$$500x = \dfrac{5.100}{3} + \dfrac{8000}{3}$             $\Rightarrow$$500x = \dfrac{8500}{3}17 \Rightarrow x > 5$ Minimum possible = 6

Multiple choice
  1. All tasks are completed

  2. T1 and T6 are left out

  3. T1 and T8 are left out

  4. T4 and T6 are left out

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Multiple choice
  1. 18 days

  2. 72/7 days

  3. 6 days

  4. 144 days

  5. 72/3 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

When X is doing 40 % of work, it takes 12 days.
When X is doing 60% of work, it takes 18 days. When X + Y + Z or X + 1/2X + 1/4X is doing 60% of work it takes 18/(1 + 1/2 + 1/4) = 72/7 days.