Quantitative Aptitude

Time, Work, and Projects

190 Questions

Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.

Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers

Time, Work, and Projects Questions

Multiple choice technology
  1. 1 Day

  2. 1 week

  3. 8 Days

  4. 3 Days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

CMR scheduling requires advance notice to ensure resource allocation and job preparation. 8 days allows sufficient time for processing, validation, and queue placement. Shorter timeframes (1-3 days) are typically insufficient for proper scheduling procedures.

Multiple choice
  1. 20

  2. 18

  3. 16

  4. 15

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

For skilled: men -> days -> amount of wall

5 -> 20  -> 1
1 -> 100 -> 1
1 -> 1   -> 1/100
For semi-skilled: men -> days -> amount of wall

8 -> 25  -> 1

1 -> 200 -> 1
1 -> 1   -> 1/200
For unskilled: men -> days -> amount of wall

10 -> 30  -> 1

1  -> 300 -> 1
1  -> 1   -> 1/300
Amount of work 2 skilled in 1 day = 2/100 Amount of work 6 semi-skilled in 1 day = 6/200 Amount of work 5 unskilled in 1 day = 5/300

Total work in 1 day 

= 2/100+6/200+5/300
= 12/600+18/600+10/600
= 1/15

So complete work will take 15 days

Multiple choice
  1. 4

  2. 5

  3. 6

  4. 7

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let each truck carry 100 units. 2800 = 4n + e n = normal 3000 = 10n + e e = excess/pending             $\therefore$$ n =\dfrac{100}{3}, e =\dfrac{8000}{3} $             5days $\Rightarrow$$500x = \dfrac{5.100}{3} + \dfrac{8000}{3}$             $\Rightarrow$$500x = \dfrac{8500}{3}17 \Rightarrow x > 5$ Minimum possible = 6

Multiple choice
  1. All tasks are completed

  2. T1 and T6 are left out

  3. T1 and T8 are left out

  4. T4 and T6 are left out

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Multiple choice
  1. 18 days

  2. 72/7 days

  3. 6 days

  4. 144 days

  5. 72/3 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

When X is doing 40 % of work, it takes 12 days.
When X is doing 60% of work, it takes 18 days. When X + Y + Z or X + 1/2X + 1/4X is doing 60% of work it takes 18/(1 + 1/2 + 1/4) = 72/7 days.

Multiple choice
  1. 10:00 a.m. – 12 noon

  2. 12 noon – 2:00 p.m.

  3. 1:00 p.m. – 3:00 p.m.

  4. 2:00 p.m. – 4:00 p.m.

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Clearly, the computers would be used the most when all the three groups are working simultaneously and this happens during the period of 12 noon to 2:00 p.m.

Multiple choice
  1. 6 days

  2. 14 days

  3. 5 days

  4. 10 days

  5. 8 days

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

It is correct answer.

Let alone time of Suman be x .

Then alone time of Rahul = x/3 and that of Varun be x/4.

Suman's one day work + Rahul's one day work + Varun's one day work = Combined one day work                     

   (1/x) + (1/(x/3)) + (1/(x/4)) = 1                                                  x = 8

Multiple choice
  1. 30 days

  2. 10 days

  3. 15 days

  4. 1/10 days


Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

( A + B ) 's  1 day work  = 1 / 6( B + C ) 's 1 day work = 2 / 15       ( 7 1/2 = 15 /2 ) ( C + A )'s 1 day work = 1/ 10By adding

( A+ B ) + ( B + C ) + ( C + A ) 's 1 day work = 1/ 6 + 2/15 + 1/10  (A + B + B + C + C + A) 's 1 day work = 1/ 6 + 2/15 + 1/10  ( 2A + 2B + 2C ) 's 1 day work = 1/6 + 2/15 + 1/10 2 ( A + B + C ) 's 1 day work = (5 + 4 + 3) /30 = 12/30 = 6 /15 (A + B + C )'s 1 day work = 6/15 x 2 = 6/30

( A + B + C ) 's 1 day work - ( C + A ) 's 1 day work =                                  6/30 - 1/10                                 = 6 - 3 /30                                = 3/30                                  = 1 /10 B1 day work is 1/10 B can complete whole work in  1 / 1/10 = 10 days

Multiple choice
  1. 28 days

  2. 14 days

  3. 4 days

  4. 21 days

  5. 8 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done by C in one day = 1/7 Work done by B in one day = 1/2(C) = 1/7 x 1/2 = 1/14 Work done by A in one day = 1/2(B) = 1/2 x 1/14 = 1/28 Work done by A, B and C together in one day = (4 + 2 + 1)/28 = 1/4 Work is done by A, B and C together in 4 days.

Multiple choice
  1. 35/6 days

  2. 6/35 days

  3. 6 days

  4. 60/11 days

  5. 12 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's 1 day's work = 1/10th part of the whole work and  B's 1 day's work = 1/14th part of the whole work. Therefore, (A + B)'s one day's work = 1/10 + 1/14 = 6/35th part of the whole work. So, both will complete the work in 35/6 days. It is the correct answer.